    Refinery Status: Flint Hills Shuts Gasoline Unit

    Published September 10, 2010    Dow Jones Newswires
     

    The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn’t purport to be a comprehensive list.
    Flint Hills Resources Friday will shut FCCU No. 2 and Sulfur Recovery Unit No. 1 in the East Plant section of its Corpus Christ, Texas, refinery for maintenance that is expected to conclude on September 24. The start and end dates of the work are estimates only.
    ConocoPhillips Thursday filed a planned flaring event notification for emissions that will exceed allowable limits at its refinery in Wilmington, Calif., near Los Angeles. The 20-day event, which will start tomorrow, Sept. 10, is not due to equipment failure, a filing to the South Coast Air Quality Management District said.
    Shell Oil (RDSB, RDSA) Products US Thursday reported the shutdown of a wet gas compressor at its Martinez, California, oil refinery due to mechanical failure, a filing to California state environmental regulators said.
    Murphy Oil Corp. said Thursday that crude oil throughput rates at its oil refinery in Meraux, La., have been reduced to about 90,000 barrels a day from its boiler plate capacity of 125,000 barrels a day, since late Wednesday when a leak was discovered at the plant’s key gasoline-making unit. The 35,000-barrels-a-day FCCU will resume normal operations by Friday evening, the company said.

    Valero Energy said Thursday that a diesel hydrotreater and a crude distillation unit at its Port Arthur, Texas refinery were in circulation mode, and that two sulfur recovery units were operating, after going off line the day before owing to a brief power failure.

    BP PLC said Wednesday that more planned flaring would take place at its Carson, California, refinery starting Sunday, September 12 and ending on Friday, October 1. The flaring is not associated with equipment breakdown, a filing to state environmental regulators said.
    Citgo Corp. Tuesday announced the completion of construction and start up of a new ultralow-sulfur diesel unit at its oil refinery in Lemont, Illinois.
    Citgo Corp. was forced to shut down both flare gas recovery compressor units in the East Plant section of its Corpus Christi, Texas, oil refinery over the past few days due to mechanical problems, a Tuesday filing to state environmental regulators said.
    ConocoPhillips reported late Monday afternoon that part of the sulfur recovery unit at its Belle Chase, La., refinery was being shut down for repairs, according to a filing with environmental regulators. The company reported no impact to the local community from emissions.
    ExxonMobil Corp. said Monday that its joint-venture refinery in Chalmette, La., was operating and that customers’ needs were being met following an early morning internal power failure. The outage resulted in a release of spent catalyst and the shut down of several unspecified process units, according to a Saint Bernard Parish fire chief. The company did not supply details on how the failure affected operations at the plant, co-owned by Petroleos de Venezuela, S.A.
    Imperial Oil began the sequential restart of its 89,000-barrels-a-day refinery in Nova Scotia late Saturday in the wake of Tropical Storm Earl. The plant was shut, and all non-essential personnel were released Friday as a precautionary measure ahead of the storm.
    For more detailed information, search Dow Jones Newswires using the code N/REF. Operator Refinery Capacity Description Restart (in 000s bbl/day)
    UNPLANNED
    CANADA
    Imperial Nova Scotia 89.0 Refinery in restart Sept 4 Sep 5 after shutting down ahead of Hurricane Earl for safety reasons.
    EAST COAST
    Sunoco Philadelphia 330.0 Co. confirms Aug 28 reformer n/a PA unit upset; status of unit unclear. United Warren, PA 70.0 Crude throughput reduced by n/a 35% owning to Enbridge pipe- line leak/closure on July 26.
    CARIBBEAN
    Hovensa St. Croix 500.0 Unidentified unit shut because VI of pipe leak Aug. 17.
    GULF COAST
    Citgo Corpus 163.0 Flare Gas Recovery System n/a Christi, TX shut due to the loss of two compressors on about Sept. 6. No restart estimate.
    Conoco Belle Chasse 247.0 Part of a sulfur recovery n/a LA unit was shut for repairs on Sept. 6. No restart esti- mate.
    Murphy Meraux, LA 125.0 Crude throughput reduced to Sep 10 90,000-b/d Sept 8 while FCCU in circulation for repairs.
    Shell Deer Park 340.0 Unidentified unit taken out of n/a TX service after a fire on July 20. Refinery operations were “stab- ilizing” following the fire, the co. said.
    Valero Port Arthur 325.0 Crude Unit, Diesel Hydrotreater Sep 10 TX in circulation; two sulfur re- covery units restarted after Sept 8 power outage.
    Valero Corpus 315.0 Naphtha hydrotreater was shut at Christi, TX Complex 7 of the East Plant Aug. 17 to repair heat exchanger leak, Co. said Aug. 18. No material impact on production is expected.
    MIDWEST
    BP Whiting, IN 405.0 White Oak pipeline transporting finished product to 2 Illinois terminals was ahead of an excavation that began Aug. 17 to find a leak., Co. said Aug. 18. BP/Husky Toledo, OH 160.0 Crude oil throughput reduced n/a by unspecified amount owing to Enbridge’s crude oil pipeline leak/closure on July 26.
    Exxon Joliet, IL 239.0 Co. confirms Fri. compressor n/a snag on Aug 28 at unspecified equipment. All other operations normal while compressor repairs continue.
    Marathon St. Paul, MN 74.0 On-site emergency crew extin- Sep 1 guishes fire on Sept. 1. No injuries or off-site impact. Impact on operations unclear.
    ROCKIES
    WEST COAST
    Shell Martinez 156.4 Wet gas compressor shut Sept 9 n/a CA due to mechanical failure; flar- ing and emissions were reported to environmental regulators.
    Conoco Ferndale, 100.0 An alkylation unit and butamer n/a WA shut following a pump fire early June 15, an environmental agency said. The refinery continues to operate, co. said June 15.
    Tesoro Anacortes 120.0 Company expects to restart the Early the refinery in Oct following Oct a fatal blast in April, the co. said Aug 27. Initially, the plant was seen restarting in Sept.
    PLANNED
    CANADA
    Shell Montreal 130.0 The refinery will be converted into Quebec terminal. CARIBBEAN Valero Aruba 235.0 Idled refinery to resume opera- tions after completing turnaround maintenance in Sept. if it is profitable to do so, the co. said on July 27.
    EAST COAST
    Sunoco Westville 145.0 Idling all Eagle Point refin- n/a NJ ing operations indefinitely due to poor economics, co. said Oct. 6.
    Valero Delaware 210.0 PBF Investments has closed Apr 2011 deal to buy plant. Petroplus said May 5 the plant would be restarted in 2Q of 2011. Western Yorktown 64.5 The refinery will close in Sept VA September 2010 for economic reasons. Terminal operations will continue. Maintenance had been planned for 3Q 2010.
    GULF COAST
    Conoco Borger, TX 146.0 Two upsets at Unit 40, FCCU re- sult in brief emissions and opacity on Aug. 4. Status of unit unclear. Maintenance activity continues, the co. said on Aug 3. The work has been underway since June 5.
     Chevron Pascagoula 330.0 Pre-commercial heavy oil 2010 Miss. conversion project delayed from 2008 to 2010 due to economic factors. Expansion project including the replacement of two 30-year- old reformers and construction of a 55,000 b/d continuous catalytic reformer platformer unit to be completed by late summer, Industrial Info Resources said July 6. A premium base-oil facility was also being planned, co. said in late Feb.
    Conoco Sweeny, TX 247.0 Personnel will manually op- Sep 3 erate EP rappers at FCCU No. 27 on Sept 3 for three hours starting at 11:00 a.m.
    Exxon Baytown, TX 560.6 Extended period of scheduled Est. maintenance at crude unit, End Oct several hydrofiners and other units starts week of Aug 22. Return to normal operations unclear, sources say work will take two months to complete.
    Exxon Chalmette 120.0 Crude throughput will be re- N/A LA duced to 90,000-b/d as redun- dant units and about 70 jobs are taken out of service and cut for economic reason. These have begun to take place, the co. said Aug 26.
    Flint Corpus 290.0 FCCU No. 2, Sulfur Recovery Sep 24 Hills Christi, TX No. 1 to shut for maintenance on Sept. 10. $250 mln project for new Spring 2010 diesel desulfurization, sulfur recovery unit to begin in Fall 2008. Construction to last 18 months.
    Motiva Port Arthur 285.0 Expansion project to increase 1Q throughput capacity by 325,000 2012 b/d, to 610,000-b/d, slowed. Completion now seen 1Q 2012, from 2010.
    Valero Corpus 340.0 West Plant 50,000-b/d FCCU at Christi, TX reduced rates since mid-Dec for economic reasons.
    Valero Norco, LA 250.0 Hydrocracker project will pro- 2013 ceed and be completed in late 2013, the co. said on July 27. FCCU will be revamped during 2Q 2Q of 2011, the co. said on 2011 July 27. Upgrade project to build 2012 a new diesel hydrotreater unit moved from 2010 to 4Q 2012.
    Valero Port Arthur 325.0 Hydrocracker project will pro- 2012 TX ceed and be completed in late 2012, the co. said on July 27. Six coke drums will be re- 2011 placed in 2011. 77,000-b/d FCCU at reduced n/a rates since mid-Dec for economic reasons.
    Valero Sunray, TX 170.0 55,000-b/d FCCU at reduced n/a rates since mid-Dec for economic reasons. Expanded crude gather system 4Q will increase available crude 2010 supplies to refinery by 4Q.
    Murphy Meraux, LA 125.0 Plant operations returned to normal after catalyst change that lasted a couple of weeks, Co. said Aug. 24. Production is at about 120,000 b/d.
    MIDWEST
    BP Toledo, OH 155.0 $400 million upgrade 2012 to start 2010.
    Citgo Lemont, IL 167.0 New ultralow-sulfur diesel Sep 7 unit start up announced on Sept. 7.
    CVR Coffeyville 115.0 New ultra low sulfur gasoline KS unit will be brought online in 2Q, co. said May 3. Previous target was to have unit up by end of 2010.
    Husky Lima, OH 160.0 Scheduled fall turnaround main- Dec tenance on track to begin in Oct for 40 days, the co. said on Aug 26.
    Valero Ardmore, OK 90.0 Plant-wide turnaround planned; 2011 work will impact 1Q 2011 results.
    ROCKY MOUNTAIN
    Suncor Commerce 93.0 Planned work at reformer unit Fall City, CO deferred to Fall 2010 from Feb 2010 28 start date.
    WEST COAST
    BP Carson, CA 265.0 More planned flaring expected Oct 1 between Sept 5 and Oct 1.
    Conoco Wilmington 139.0 Planned flaring expected Sept. Sept 30 CA 10-30. The event is not due to equipment breakdown.
    Valero Benicia 170.0 Scrubber installation continues; 2010 CA work seen concluding by year-end, the co. said on July 27.
    Tesoro Golden Eagle 166.0 Major turnaround maintenance 2011
    Martinez, CA deferred to 2011 from late 2009, the co. said Feb. 3.
    Tesoro Wilmington 97.0 Flaring will start on Sept 7 Sept 11 CA for four days; the event is not due to equipment breakdown.
    Copyright 2010 Dow Jones Newswires