Here is Bloomberg Nov 08 update on NA Planned & Unplanned S/D + Future Outages.
—————
North American Planned, Unplanned Refinery Shutdowns (Table)By Robert Tuttle
November 6, 2008 (Bloomberg) — Following is a table of scheduled and unplanned
refinery shutdowns, maintenance, new plants and capacity expansions in North
America. The list only includes work that could be confirmed.
Shutdown Type: P: Planned, U: Unplanned, N: Non-maintenanceRefinery Refinery
Owner Shutdown Capacity
Location Type Period b/d Notes
——————————————————————————–
New Information:Valero Delaware City P Nov 04, 08 190,200 CDU, capacity 180,000
Valero Energy Corp to b/d, shuts for 25 day
Delaware, U.S. Nov 30, 08 maintenance in November, FCC shuts
for 15 days. This was delayed from October.Current Outages:
Valero Delaware City P Nov 04, 08 190,200 CDU, capacity 180,000
Valero Energy Corp to b/d, shuts for 25 day
Delaware, U.S. Nov 30, 08 maintenance in November,
FCC shuts for 15 days.
This was delayed from
October.Conoco Borger P Nov 04, 08 146,000 FCC maintenance on
ConocoPhillips, to electrostatic
EnCana Corp Nov 18, 08 precipitators.
Texas, U.S.Marathon Texas City U Nov 03, 08 72,000 CDU, capacity 52,000 b/d,
Marathon Oil Corp, to shuts after fire.
Ashland Inc Nov, 08
Texas, U.S.Imperial Oil Sarnia P Oct 30, 08 121,000 Runs cut by partial
Exxon Mobil Corp to turnaround at main units.
Ontario, Canada Nov 30, 08 More specific details not disclosed.Valero Paulsboro U Oct 30, 08 195,000 FCC shuts because of
Valero Energy Corp to upset.
New Jersey, U.S. Nov, 08Flint Hills Corpus P Oct 27, 08 300,000 FCC No. 2, SRU shut for
Christi to maintenance.
Koch Industries Inc Nov 07, 08
Texas, U.S.Shell Canada Scotford P Oct 24, 08 100,000 Partial outage, unit shut
Royal Dutch Shell PLC to not identified.
Alberta, Canada Nov, 08PEMEX Hidalgo Tula P Oct 21, 08 273,000 CDU, VDU shut for
Petroleos Mexicanos to maintenance.
Mexico Nov 19, 08Husky Lima P Oct 18, 08 160,000 Hydrocracker shuts for
Husky Energy Inc to repair for three weeks.
Ohio, U.S. Nov 08, 08Motiva Norco P Oct 03, 08 220,000 This planned turnaround
Saudi Arabian Oil Co, to delayed to replenish fuel
Royal Dutch Shell PLC Nov 10, 08 inventory after Hurricane
Louisiana, U.S. Ike. FCC, capacity
110,000 barrel-a-day, was
to shut for maintenance.Farmland Coffeyville P Qtr 4, 08 115,000 Turnaround for
CVR Energy Inc to maintenance on nitrogen
Kansas, U.S. Qtr 4, 08 fertilizer. Event happens
every two years.Holly Woods Cross P Qtr 4, 08 26,000 Hydrocracker, capacity
Holly Corp to 15,000 barrels a day,
Utah, U.S. Qtr 4, 08 planned to start
production. Crude
refining capacity to rise
to 31,000 barrels a day.Valero Ardmore P Oct, 08 85,000 FCC shuts for 20 days and
Valero Energy Corp to hydrocracker for 30 days
Oklahoma, U.S. Nov, 08 during October and
November.Paramount P Qtr 4, 08 55,000 Hydrocracker startup to
Alon USA Energy Inc to increase gasoline, diesel
California, U.S. Qtr 4, 08 output by 50 percent.Conoco Wood River P Qtr 3, 08 306,000 Catalytic cracker
EnCana Corp, to maintenance to install
ConocoPhillips Qtr 4, 08 wet-gas scrubbers to
Illinois, U.S. reduce emissions.PEMEX Hidalgo Tula P Sep, 08 273,000 FCC shuts for planned
Petroleos Mexicanos to maintenance of up to 90
Mexico Dec, 08 days.LyondellBasell P Jul, 08 287,000 Coker shutdown extended
Houston to through November.
Access Industries Nov 30, 08
Holdings LLC
Texas, U.S.Somerset KY N Apr 01, 07 5,500 As per the Company’s Rep.
Somerset Oil Inc to The facility has been
Kentucky, U.S. N/A shutdown due to Bankrupcty
procedure. They did not sell the
refinery to USA Energy Corp as
being reported by EIA.Future Outages:
Western Refining El P Qtr 1, 09 122,000 Maintenance planned
Paso to
Western Refining Inc Qtr 1, 09
Texas, U.S.Navajo Artesia P Jan, 09 75,000 New hydrocracker,
Holly Corp to capacity 15,000 barrels a
New Mexico, U.S. Jan, 09 day, expected to start
production. Turnaround
planned.Valero Benicia P Qtr 1, 09 153,000 Full shutdown scheduled
Valero Energy Corp to for 2009 in five-year
California, U.S. Qtr 4, 09 cycle of maintenance.Sunoco Philadelphia P Qtr 1, 09 330,000 New Hydrocracker
Sunoco Inc to conversion project to
Pennsylvania, U.S. Qtr 4, 09 start operations in 2009,
upgrading 45,000 b/d of
product into ultra-low
sulfur diesel.Conoco Borger P Qtr 1, 09 146,000 New capacity,
ConocoPhillips, to debottlenecking to add
EnCana Corp Qtr 4, 09 20,000 b/d bitumen
Texas, U.S. capacity.Valero Krotz Springs P Qtr 1, 09 83,100 Full turnaround planned
Alon USA Energy Inc to for 2009.
Louisiana, U.S. Qtr 4, 09Valero Texas City P Feb, 09 230,000 CDU, VDU shut for 35
Valero Energy Corp to days, coker shuts for 40
Texas, U.S. Feb, 09 days. Maintenance delayed
from 2008 because of Hurricane Ike.PEMEX Cardenas P Feb 02, 09 190,000 New units to expand
Minatitlan to capacity to 260,000 b/d
Petroleos Mexicanos Feb 28, 09 scheduled to start in
Mexico February 2009.Valero Norco St P Qtr 3, 09 190,000 New CDU expansion to add
Charles to 45,000 b/d crude capacity,
Valero Energy Corp Qtr 3, 09 10,000 b/d coking to start
Louisiana, U.S. in third quarter 2009.Western Refining P Qtr 3, 09 61,900 Turnaround scheduled for
Yorktown to third quarter 2009, no
Western Refining Inc Qtr 3, 09 more specific details
Virginia, U.S. available.BP Texas City P Sep 08, 09 470,000 FCCU No. 3 shuts for
BP PLC to turnaround.
Texas, U.S. Oct 01, 09Marathon Garyville P Qtr 4, 09 275,000 New CDU, VDU,
Marathon Oil Corp, to hydrocracker (capacity
Ashland Inc Qtr 4, 09 70,000 b/d), delayed
Louisiana, U.S. coker (44,000 b/d),
reformer (65,000 b/d),
kerosene hydrotreater
(47,000) planned to come
on line, raising refinery
throughput to 425,000
barrels a day.Conoco Wood River P Qtr 1, 10 306,000 New Coker, 65,000 b/d
EnCana Corp, to capacity, scheduled to
ConocoPhillips Qtr 4, 10 come on stream in 2010.
Illinois, U.S. Refinery capacity to
increase to 360,000 b/d.Flint Hills Corpus P Qtr 1, 10 300,000 New diesel dsulfurization
Christi to unit and sulfur recovery
Koch Industries Inc Qtr 1, 10 plant planned to be
Texas, U.S. completed early 2010.Valero Benicia P Qtr 1, 10 153,000 New units to expand CDU
Valero Energy Corp to capacity 25% to daily
California, U.S. Qtr 4, 10 runs of 180,000 b/d,
coker by 25%, SRU by 50%
to handle heavier crudes,
reduce gasoil imports and
expand gasoline output.Motiva Port Arthur P Qtr 1, 10 285,000 New units to add 325,000
Motiva Enterprises to b/d crude capacity, to
LLC Qtr 4, 10 start in 2010.
Texas, U.S.Placid Port Allen P Qtr 1, 10 57,000 New FCC, units to expand
Placid Refining Co to capacity to 80,000
LLC Qtr 4, 10 barrels a day scheduled
Louisiana, U.S. to be completed in 2010.Farmland Coffeyville P Qtr 1, 10 115,000 Full turnaround scheduled
CVR Energy Inc to for 2010, in cycle of every
Kansas, U.S. Qtr 4, 10 three to four years. Last event
was Feb-April 2007.Pasadena P Qtr 1, 10 106,500 New units to double
Nationale A to capacity to 200,000
Portefeuille Qtr 4, 10 barrels a day planned to
Texas, U.S. start in 2010.Chevron Richmond P Qtr 1, 10 257,200 New Hydrogen plant,
Chevron Corp to reforming units to
California, U.S. Qtr 4, 10 improve crude feedstock
flexibility scheduled to
start in 2010. No change
to refinery capacity.Chevron Pascagoula P Qtr 2, 10 330,000 New Platformer/CCR unit
Chevron Corp to to start output in
Mississippi, U.S. Qtr 3, 10 mid-2010, to increase
gasoline output 10%, or
600,000 gallons a day.Valero Norco St P Qtr 4, 10 190,000 New Hydrocracker planned
Charles to to enter service in
Valero Energy Corp Qtr 4, 10 fourth quarter 2010.
Louisiana, U.S.Sinclair Tulsa P Qtr 4, 10 60,000 New CDU, hydrocracker,
Sinclair Oil Corp to coker units planned to
Oklahoma, U.S. Qtr 4, 10 start operations.
Capacity to increase to
115,000 barrels a day.Marathon Detroit P Qtr 4, 10 100,000 New Coker, capacity
Marathon Oil Corp, to 28,000 b/d, scheduled to
Ashland Inc Qtr 4, 10 enter service, along with
Michigan, U.S. sulfur recovery unit (280
long tons/day),distillate hydrotreater
(33,000 b/d) and hydrogen plant. Nameplate capacity
Nameplate capacity of refinery to increase to 115 Mb/d.Valero Memphis P Qtr 1, 11 190,000 FCC revamp planned for
Valero Energy Corp to 2011, delayed from 2009.
Tennessee, U.S. Qtr 4, 11Total Port Arthur P Qtr 1, 11 240,000 New Coker (50,000 b/d),
Total SA to desulfurization and
Texas, U.S. Qtr 4, 11 vacuum distillation unit.
The $2.2 billion project
is scheduled to be
completed in 2011.Valero Port Arthur P Qtr 1, 11 325,000 New Hydrocracker
Valero Energy Corp to construction to be completed,
Texas, U.S. Qtr 4, 11 capacity 50,000 b/d, to start
in 2011. Had been scheduled
for 4th quarter 2010.Valero Port Arthur P Qtr 2, 11 325,000 New Coker construction to
Valero Energy Corp to be completed, capacity
Texas, U.S. Qtr 2, 11 45,000 barrels a day,during 2Q of 2011.
Refinery throughput to rise to 415,000 b/d in
conjunction with related investments. PROJECT
SHELVED IN OCT 2008.BP Whiting P Qtr 4, 11 420,000 New Coker, capacity
BP PLC to 120,000 b/d, along with
Indiana, U.S. Qtr 4, 11 related units to process
Canadian heavy oil scheduled to begin
service in late 2011.Consumers’ Co-op P Jan, 12 100,000 New CDU expansion to add
Regina to 30,000 b/d capacity to a
Federated Dec, 12 total 130,000 b/d, also
Co-operative Ltd add FCC complex, planned
Saskatchewan, Canada to start operations in 2012.Conoco Borger P Qtr 1, 12 146,000 New units to expand crude
ConocoPhillips, to distillation to 200,000
EnCana Corp Qtr 4, 12 b/d, with 75,000 b/d
Texas, U.S. bitumen capacity.Valero Quebec City P Qtr 1, 12 215,000 New Hydrocracker,
Valero Energy Corp to de-asphalting units
Quebec, Canada Qtr 4, 12 planned for 2012 startup.Historical Outages:
Pasadena P Oct 24, 08 106,500 FCC shuts for
Nationale A to maintenance.
Portefeuille Oct, 08
Texas, U.S.Marathon Texas City U Oct 23, 08 72,000 Partial outage,
Marathon Oil Corp, to unidentified unit shuts.
Ashland Inc Oct, 08
Texas, U.S.Valero Wilmington P Oct 22, 08 135,000 FCC shuts for repairs.
Valero Energy Corp to Restart confirmed.
California, U.S. Nov 03, 08Hovensa St. Croix N Oct 15, 08 495,000 Full shutdown for
Petroleos de to Hurricane Omar. Restart
Venezuela SA, Hess Oct 20, 08 began Oct. 16 and will take several
Corp. US Virgin Islands, days according to the company. U.S.Valero McKee U Oct 14, 08 164,000 FCC rates cut to minimum
Valero Energy Corp to level on power cable
Texas, U.S. Oct, 08 failure.Consumers’ Co-op N Oct, 08 100,000 Runs cut for unpsecified
Regina to reason. Additional
Federated Oct, 08 details not disclosed.
Co-operative Ltd
Saskatchewan, CanadaConoco Borger P Oct 06, 08 146,000 FCC repairs to
ConocoPhillips, to electrostatic
EnCana Corp Oct 16, 08 precipitators.
Texas, U.S.Valero Three Rivers P Oct 03, 08 95,000 Hydrocracker shuts for 28
Valero Energy Corp to days in October.
Texas, U.S. Oct, 08Husky Lima N Oct 03, 08 160,000 Runs cut 25,000 b/d after
Husky Energy Inc to pipeline leak halted
Ohio, U.S. Oct 07, 08 crude supply. Refinery
ramped up on Oct. 6 after
pipeline repaired.Hovensa St. Croix N Oct, 08 495,000 FCC runs cut on weak
Petroleos de to margins. Duration of
Venezuela SA, Hess Oct, 08 cuts, confirmed Oct. 29,
Corp not disclosed.
US Virgin Islands,
U.S.Chevron Salt Lake P Oct, 08 45,000 Coker shuts for
City to maintenance. Restart
Chevron Corp Oct, 08 confirmed.
Utah, U.S.Imperial Oil P Oct 01, 08 184,000 Diesel unit shuts for
Strathcona to maintenance. Restart
Exxon Mobil Corp Nov 03, 08 confirmed.
Alberta, CanadaValero Houston U Sep 30, 08 90,000 FCC shuts for unplanned
Valero Energy Corp to repairs after fault found
Texas, U.S. Oct 20, 08 during restart because of
Hurricane Ike.Exxon Mobil Torrance P Sep 29, 08 155,000 Coker, reformer, fuel
Exxon Mobil Corp to gas, pretreatment units
California, U.S. Oct 25, 08 shut for maintenance.Murphy Meraux P Sep 15, 08 125,000 Turnaround for
Murphy Oil Corp to unidentified unit as of
Louisiana, U.S. Oct, 08 mid-September.Valero Ardmore N Sep 15, 08 85,000 Runs cut on lack of crude
Valero Energy Corp to supply after Hurricane
Oklahoma, U.S. Sep, 08 Ike.Total Port Arthur N Sep 12, 08 240,000 Full shutdown for
Total SA to Hurricane Ike.
Texas, U.S. Oct, 08Calcasieu Lake N Sep 12, 08 29,400 Full shutdown for
Charles to Hurricane Ike. Restart
Calcasieu Refining Co Sep 17, 08 confirmed.
Louisiana, U.S.Chevron Burnaby N Sep 12, 08 55,000 FCC shut down for
Chevron Corp to maintenance after upset.
British Columbia, Sep 17, 08 Unit restarted.
CanadaExxon Mobil Beaumont N Sep 11, 08 365,000 Full shutdown for
Exxon Mobil Corp to Hurricane Ike. Limited
Texas, U.S. Oct, 08 operations resumed.Marathon Texas City N Sep 11, 08 72,000 Full shutdown for
Marathon Oil Corp, to Hurricane Ike. Restarted
Ashland Inc Oct, 08 first week of October.
Texas, U.S.Pasadena N Sep 11, 08 106,500 Full shutdown for
Nationale A to Hurricane Ike.
Portefeuille Sep, 08
Texas, U.S.BP Texas City N Sep 11, 08 470,000 Full shutdown for
BP PLC to Hurricane Ike.
Texas, U.S. Sep, 08Valero Port Arthur N Sep 11, 08 325,000 Full shutdown for
Valero Energy Corp to Hurricane Ike.
Texas, U.S. Sep, 08Motiva Port Arthur N Sep 11, 08 285,000 Full shutdown for
Motiva Enterprises to Hurricane Ike.
LLC Sep, 08
Texas, U.S.Exxon Mobil Baytown N Sep 11, 08 563,000 Full shutdown for
Exxon Mobil Corp to Hurricane Ike.
Texas, U.S. Sep 19, 08Valero Houston N Sep 11, 08 90,000 Full shutdown for
Valero Energy Corp to Hurricane Ike.
Texas, U.S. Sep 17, 08Valero Texas City N Sep 11, 08 230,000 Full shutdown for
Valero Energy Corp to Hurricane Ike. Restart
Texas, U.S. Sep 17, 08 confirmed.Shell Deer Park N Sep 11, 08 340,000 Full shutdown for
Royal Dutch Shell to Hurricane Ike. Restart
PLC, Petroleos Sep 17, 08 confirmed.
Mexicanos
Texas, U.S.LyondellBasell N Sep 10, 08 287,000 Full shutdown for
Houston to Hurricane Ike.
Access Industries Sep, 08
Holdings LLC
Texas, U.S.Conoco Sweeny N Sep 10, 08 216,000 Full shutdown for
Petroleos de to Hurricane Ike. Restart
Venezuela SA, Sep 16, 08 confirmed.
ConocoPhillips
Texas, U.S.Conoco Bayway Linden U Sep 07, 08 238,000 Isomerization unit shut
ConocoPhillips to by fire. Extent of damage
New Jersey, U.S. Sep, 08 not reported.Calcasieu Lake N Sep 03, 08 29,400 Full shutdown for
Charles to Hurricane Gustav. Restart
Calcasieu Refining Co Sep 10, 08 confirmed.
Louisiana, U.S.Suncor Sarnia P Sep 02, 08 80,000 Hydrocracker, gasoline
Suncor Energy Inc to hydrotreater shut for
Ontario, Canada Oct 12, 08 maintenance.PEMEX Cardenas P Sep, 08 190,000 Gasoline, diesel units
Minatitlan to shut for planned
Petroleos Mexicanos Sep, 08 maintenance.
MexicoExxon Mobil Joliet P Sep 01, 08 240,000 FCC, alkylation units
Exxon Mobil Corp to shut for maintenance.
Illinois, U.S. Oct, 08 Restart confirmed Oct. 14.Chevron Pascagoula N Sep 01, 08 330,000 Runs cut in connection
Chevron Corp to with Hurricane Gustav.
Mississippi, U.S. Sep 05, 08Exxon Mobil Baton N Aug 31, 08 488,600 Full shutdown for
Rouge to Hurricane Gustav. Restart
Exxon Mobil Corp Sep 05, 08 confirmed.
Louisiana, U.S.ConocoPhillips N Aug 29, 08 247,000 Full shutdown for
Alliance to Hurricanes Gustav and
ConocoPhillips Sep 16, 08 Ike. Restart confirmed.
Louisiana, U.S.Chalmette LA N Aug 29, 08 184,000 Full shutdown for
Petroleos de to Hurricane Gustav.
Venezuela SA, Exxon Sep, 08
Mobil Corp
Louisiana, U.S.Valero Krotz Springs N Aug 29, 08 83,100 Full shutdown for
Alon USA Energy Inc to Hurricane Gustav. Restart
Louisiana, U.S. Sep 08, 08 confirmed.Total Port Arthur P Aug 29, 08 240,000 Full shutdown for
Total SA to Hurricane Gustav.
Texas, U.S. Sep 08, 08Valero Texas City N Aug 29, 08 230,000 Runs cut for Hurricane
Valero Energy Corp to Gustav. Normal operations
Texas, U.S. Sep 08, 08 resumed.Valero Norco St N Aug 29, 08 190,000 Full shutdown for
Charles to Hurricane Gustav.
Valero Energy Corp Sep 08, 08
Louisiana, U.S.Motiva Norco N Aug 29, 08 220,000 Full shutdown for
Saudi Arabian Oil Co, to Hurricane Gustav.
Royal Dutch Shell PLC Sep 08, 08
Louisiana, U.S.Valero Houston N Aug 29, 08 90,000 Runs cut because of
Valero Energy Corp to Hurricane Gustav. Normal
Texas, U.S. Sep 08, 08 operations resumed.Valero Port Arthur N Aug 29, 08 325,000 Runs cut for Hurricane
Valero Energy Corp to Gustav. Restart
Texas, U.S. Sep 08, 08 confirmed.Motiva Convent N Aug 29, 08 235,000 Full shutdown in
Motiva Enterprises to preparation for Hurricane
LLC Sep 07, 08 Gustav. Restart confirmed.
Louisiana, U.S.Exxon Mobil Baytown N Aug 29, 08 563,000 Runs cut for Hurricane
Exxon Mobil Corp to Gustav.
Texas, U.S. Sep 05, 08Exxon Mobil Beaumont N Aug 29, 08 365,000 Runs cut for Hurricane
Exxon Mobil Corp to Gustav.
Texas, U.S. Sep 05, 08Murphy Meraux N Aug 29, 08 125,000 Full shutdown for
Murphy Oil Corp to Hurricane Gustav. Restart
Louisiana, U.S. Sep 05, 08 confirmed.Marathon Garyville N Aug 29, 08 275,000 Full shutdown for
Marathon Oil Corp, to hurricane Gustav. Restart
Ashland Inc Sep 03, 08 confirmed.
Louisiana, U.S.Motiva Port Arthur N Aug 29, 08 285,000 Runs cut to minimum rates
Motiva Enterprises to for Hurricane Gustav.
LLC Sep 03, 08
Texas, U.S.Conoco Lake Charles N Aug 29, 08 252,000 Full shutdown for
ConocoPhillips to Hurricane Gustav. Restart
Louisiana, U.S. Sep 03, 08 confirmed.Citgo Corpus Christi N Aug 22, 08 156,000 FCC shuts due to power
Petroleos de to failure. Restart
Venezuela SA Aug 25, 08 confirmed.
Texas, U.S.Valero Delaware City U Aug 20, 08 190,200 FCC output cut by
Valero Energy Corp to repairs.
Delaware, U.S. Aug 25, 08North Pole U Aug, 08 220,000 Runs cut for unspecified
Koch Industries Inc to repairs, gasoline
Alaska, U.S. Aug, 08 production reduced.Frontier El Dorado P Aug, 08 112,000 Coker installation
Frontier Oil Corp to begins.
Kansas, U.S. Aug, 08PEMEX Cardenas P Aug 16, 08 190,000 Diesel sulfur recovery
Minatitlan to units shut for
Petroleos Mexicanos Oct 01, 08 maintenance.
MexicoConoco Bayway Linden U Aug 16, 08 238,000 Un-named unit shut,
ConocoPhillips to causing flaring.
New Jersey, U.S. Aug, 08Sunoco Toledo P Qtr 3, 08 150,000 CDU, FCC units to shut in
Sunoco Inc to third quarter
Ohio, U.S. Qtr 3, 08 maintenance.Shell Canada Sarnia U Aug 15, 08 71,820 Partial shutdown after
Royal Dutch Shell PLC to unit fails. Shell wouldn’t
Ontario, Canada Aug, 08 identify the unit and said
customer needs are being met
during the outage.Conoco Wood River U Aug, 08 306,000 FCC shuts for
EnCana Corp, to maintenance.
ConocoPhillips Aug, 08
Illinois, U.S.Alon Big Spring P Aug 13, 08 70,000 Repairs to cat crack will
Alon Israel Oil Co to be complete Aug. 13 and
Ltd Aug 26, 08 oil will be put in Aug.
Texas, U.S. 26. Repairs to the alky
unit will be complete
Sept. 3 and oil will be
put in Sept. 9.Valero Corpus Christi U Aug 13, 08 110,000 CDU shuts for unplanned
East to maintenance. Restart
Valero Energy Corp Aug 21, 08 confirmed.
Texas, U.S.Conoco Borger P Aug 12, 08 146,000 Repairs to fccu’s
ConocoPhillips, to electrostatic
EnCana Corp Aug 21, 08 precipitator.
Texas, U.S.Holly Woods Cross P Aug 11, 08 26,000 Turnaround for 26 days
Holly Corp to starts in week of Aug. 11
Utah, U.S. Sep 05, 08 at Woods Cross, Utah
refinery.Chevron El Segundo P Aug 11, 08 260,000 Turnaround shuts
Chevron Corp to unidentified unit.
California, U.S. Aug, 08Citgo Corpus Christi U Aug 11, 08 156,000 CDU, vacuum unit shuts
Petroleos de to for repairs.
Venezuela SA Aug 16, 08
Texas, U.S.Exxon Mobil Baytown U Aug 11, 08 563,000 Hydrocracker shuts for
Exxon Mobil Corp to repair. Restart
Texas, U.S. Aug 12, 08 confirmed.Marathon Catlettsburg N Aug 10, 08 239,000 Runs cut after leak shuts
Marathon Oil Corp, to crude oil supply
Ashland Inc Aug 13, 08 pipeline. Restart
Kentucky, U.S. confirmed.Total Port Arthur P Aug 06, 08 240,000 Two package boilers shut
Total SA to
Texas, U.S. Aug 24, 08Citgo Corpus Christi U Aug 06, 08 156,000 Crude vacuum unit
Petroleos de to
Venezuela SA Aug 07, 08
Texas, U.S.Petro-Canada Edmonton P Aug 05, 08 135,000 Turnaround for 60 days
Petro-Canada to began Aug. 3. Restart
Alberta, Canada Nov 03, 08 confirmed Nov. 3. Full
rates planned for end November.Petro-Canada Edmonton P Qtr 3, 08 135,000 Full shutdown of 135,000
Petro-Canada to bbl/day refinery during the second
Alberta, Canada Oct, 08 half 2008 to allow new units to be
added to the plant as part of an upgrade.Marathon Texas City N Aug 04, 08 72,000 Full shutdown because of
Marathon Oil Corp, to storm. Restart confirmed.
Ashland Inc Aug 06, 08
Texas, U.S.Valero Port Arthur N Aug 04, 08 325,000 Rates reduced because of
Valero Energy Corp to storm
Texas, U.S. Aug 05, 08Valero Houston N Aug 04, 08 90,000 Rates reduced because of
Valero Energy Corp to storm.
Texas, U.S. Aug 05, 08Valero Texas City P Aug 04, 08 230,000 Rates reduced because of
Valero Energy Corp to storm
Texas, U.S. Aug 05, 08Exxon Mobil Torrance P Aug, 08 155,000 Hydrodesulfurization unit
Exxon Mobil Corp to shuts for repairs.
California, U.S. Aug 31, 08Petro-Canada Edmonton U Aug 03, 08 135,000 FCC shuts because of
Petro-Canada to fault, leading to regional gasoline
Alberta, Canada Aug 27, 08 shortages. Restart confirmed.Holly Woods Cross P Aug, 08 26,000 Turnaround planned.
Holly Corp to
Utah, U.S. Sep, 08Placid Port Allen P Aug, 08 57,000 Turnaround scheduled for
Placid Refining Co to 30 days during
LLC Sep, 08 August-September.
Louisiana, U.S.BP Texas City P Jul 29, 08 470,000 FCC Electrostatic
BP PLC to Precipitator Stack trips
Texas, U.S. Aug, 08 and rates reduced.Irving Saint John N Jul 29, 08 250,000 Runs cut after power
Irving Oil Corp to loss.
Newfoundland and Aug, 08
Labrador, CanadaConocoPhillips U Jul 28, 08 247,000 FCC shut because of leak
Alliance to
ConocoPhillips Aug, 08
Louisiana, U.S.Valero Port Arthur P Jul 23, 08 325,000 Runs cut 10%-20% by
Valero Energy Corp to Hurricane Dolly.
Texas, U.S. Jul, 08Valero Houston N Jul 23, 08 90,000 Runs cut 10%-20% by
Valero Energy Corp to Hurricane Dolly.
Texas, U.S. Jul, 08BP Texas City U Jul 22, 08 470,000 FCC No. 1 runs cut
BP PLC to because of fault.
Texas, U.S. Jul, 08Valero Aruba U Jul 19, 08 275,000 Runs cut by 5,000 barrels
Valero Energy Corp to a day for minor
Aruba Jul, 08 maintenance. Operations
return to normal.Shell Deer Park N Jul 17, 08 340,000 FCC rates reduced after
Royal Dutch Shell to power disruption. Restart
PLC, Petroleos Jul 19, 08 confirmed.
Mexicanos
Texas, U.S.LyondellBasell P Jul, 08 287,000 CDU, coker shut for
Houston to maintenance. Crane
Access Industries Sep, 08 collapse during repairs
Holdings LLC kills 4 and delays work.
Texas, U.S. Rest of refinery operated
normally during the event.BP Toledo P Jul 15, 08 155,000 Hydrocracker, reformer
BP PLC to shut for maintenance.
Ohio, U.S. Sep 04, 08Murphy Meraux P Jul, 08 125,000 Runs cut 10% on weak
Murphy Oil Corp to margins.
Louisiana, U.S. Aug, 08Murphy Superior P Jul, 08 35,000 Runs cut 25% on weak
Murphy Oil Corp to margins.
Wisconsin, U.S. Aug, 08Citgo Corpus Christi P Jul 15, 08 156,000 FCC shuts for
Petroleos de to maintenance. Unit
Venezuela SA Jul 17, 08 restarts July 16.
Texas, U.S.PEMEX Hidalgo Tula N Jul 15, 08 273,000 Power cut shuts several
Petroleos Mexicanos to units. Restart confirmed.
Mexico Jul 17, 08Conoco Borger P Jul 13, 08 146,000 Repairs scheduled on the
ConocoPhillips, to electrostatic
EnCana Corp Jul 22, 08 precipitators of unit 29,
Texas, U.S. a fluid catalytic cracker.Total Port Arthur P Jul 09, 08 240,000 Hydrotreater and eight
Total SA to other units shut. Units
Texas, U.S. Jul 27, 08 restarting July 27 to July 31.Petro-Canada Edmonton U Jul 09, 08 135,000 Full shutdown after
Petro-Canada to boiler failure. Restart
Alberta, Canada Jul 16, 08 confirmed.Valero Ardmore U Jul 08, 08 85,000 FCCU shut after power
Valero Energy Corp to disruption, restart
Oklahoma, U.S. Jul 11, 08 confirmed.Tesoro Martinez U Jul 08, 08 166,000 Gasoil hydrotreater shuts
Tesoro Corp to because of leaking valve.
California, U.S. Jul 09, 08 Restart confirmed.US Oil Tacoma N Jul 07, 08 35,000 Runs cut 50% after power
Nationale A to failure.
Portefeuille Jul, 08
Washington, U.S.Lion Oil El Dorado N Jul, 08 58,000 Asphalt production cut by
Ergon Inc to 50 percent after unit 9
Arkansas, U.S. Sep, 08 shut.BP Texas City U Jul 01, 08 470,000 Residual hydrotreater
BP PLC to restarts.
Texas, U.S. Jul 01, 08Total Port Arthur P Jun 25, 08 240,000 CDU No. 2 shuts for
Total SA to maintenance.
Texas, U.S. Jul, 08Lake Charles N Jun 25, 08 320,000 Units shut by power cut
Petroleos de to June 25. Operations
Venezuela SA Jun, 08 restarted the same day.
Louisiana, U.S.Valero Corpus Christi P Jun 23, 08 38,000 Refinery cut production
West to rates at the fluid catalytic
Valero Energy Corp Jun 23, 08 cracking unit at Corpus Christi plant
Texas, U.S. after a steam leak caused excess emissions.
Output was not reduced.BP Texas City U Jun 22, 08 470,000 FCC No. 1 pump leaks.
BP PLC to Effect on output not
Texas, U.S. Jun, 08 disclosed.Exxon Mobil Baytown N Jun 22, 08 563,000 Sulfur recovery unit
Exxon Mobil Corp to shuts. All customer needs
Texas, U.S. Jun, 08 being met, Exxon said.BP Carson N Jun 21, 08 265,500 CDU shuts after power
BP PLC to outage. Unit was in
California, U.S. Jun 23, 08 restart June 23.Conoco Ponca City N Jun 20, 08 187,000 FCC shuts after power
ConocoPhillips to cut. Restart confirmed.
Oklahoma, U.S. Jun 22, 08Shell Deer Park U Jun 18, 08 340,000 FCC wet gas compressor
Royal Dutch Shell to trips.
PLC, Petroleos Jun 19, 08
Mexicanos
Texas, U.S.Delek LaGloria N Jun 18, 08 58,000 CDU, alkylation shut by
Delek US Holdings Inc to power failure. Units
Texas, U.S. Jun 19, 08 restarted.Exxon Mobil Torrance P Jun 13, 08 155,000 Sulfur recovery unit
Exxon Mobil Corp to shuts for maintenance.
California, U.S. Jun 30, 08 Restart confirmed.Pasadena P Jun 11, 08 106,500 FCC unit upset. No
Nationale A to additional details
Portefeuille Jun, 08 available.
Texas, U.S.Delek LaGloria N Jun 10, 08 58,000 Power failure shuts
Delek US Holdings Inc to unspecified units.
Texas, U.S. Jun 11, 08 Operations restarted.
Production loss not
specified.LyondellBasell N Jun 10, 08 287,000 CDU shut during storm.
Houston to Restart confirmed.
Access Industries Jun 11, 08
Holdings LLC
Texas, U.S.Shell Deer Park N Jun 10, 08 340,000 FCC shuts in brief outage
Royal Dutch Shell to after compressor fails.
PLC, Petroleos Jun 11, 08
Mexicanos
Texas, U.S.Valero Port Arthur P Jun 08, 08 325,000 distillate hydrotreater
Valero Energy Corp to shuts for maintenance.
Texas, U.S. Jun 12, 08Valero Wilmington U Jun 06, 08 135,000 FCC, alkylation shut by
Valero Energy Corp to leak. Restart confirmed.
California, U.S. Jun 09, 08Conoco Borger P Jun 06, 08 146,000 FCC shut for repairs.
ConocoPhillips, to
EnCana Corp Jun 09, 08
Texas, U.S.ConocoPhillips U Jun 03, 08 247,000 FCC shuts for repairs.
Alliance to Restart confirmed.
ConocoPhillips Jun 18, 08
Louisiana, U.S.Valero Delaware City U Jun 03, 08 190,200 Coker rates cut because
Valero Energy Corp to of boiler fault. Restart
Delaware, U.S. Jun 06, 08 confirmed.Sunoco Marcus Hook U Jun, 08 175,000 FCC runs cut by
Sunoco Inc to operational upset. Full
Pennsylvania, U.S. Jun 27, 08 rates scheduled for the
end of June.Motiva Port Arthur N Jun 02, 08 285,000 Full shutdown after power
Motiva Enterprises to cut. Restart began June
LLC Jun 05, 08 5.
Texas, U.S.BP Texas City P May 31, 08 470,000 Hydrocracker
BP PLC to (ultracracker) shuts.
Texas, U.S. Jun 05, 08 Additional details not
available.Motiva Norco P May 30, 08 220,000 Hydrocracker shuts for
Saudi Arabian Oil Co, to mainteance late May for a
Royal Dutch Shell PLC Jul 09, 08 month. Restart confirmed.
Louisiana, U.S.Big West Oil U May 30, 08 68,000 Sulfur recovery unit
Bakersfield to shuts.
Flying J Oil & Gas May 30, 08
Inc
California, U.S.BP Carson P May 29, 08 265,500 Coker shuts for
BP PLC to maintenance. Restart
California, U.S. Jun 20, 08 confirmed.Flint Hills Corpus N May 27, 08 300,000 FCC, sulfur recovery
Christi to units shut after loss of
Koch Industries Inc Jun, 08 steam.
Texas, U.S.Valero Paulsboro U May 26, 08 195,000 FCC shuts because of a
Valero Energy Corp to leak. Restart confirmed.
New Jersey, U.S. Jun 01, 08Conoco Sweeny P May 19, 08 216,000 Hydrotreater for
Petroleos de to distillates shuts for
Venezuela SA, May 31, 08 catalyst change.
ConocoPhillips
Texas, U.S.Chevron El Segundo P May 16, 08 260,000 CDU, 70,000 b/d capacity
Chevron Corp to shuts for `several weeks’
California, U.S. Jun 22, 08 of maintenance. Restart
confirmed.Sunoco Philadelphia U May 16, 08 330,000 CDU, gulfiner units shut.
Sunoco Inc to Restarts confirmed June
Pennsylvania, U.S. Jun 04, 08 4.Valero Three Rivers P May 16, 08 95,000 FCC shuts for 10 days of
Valero Energy Corp to maintenance.
Texas, U.S. May 26, 08Countrymark Mount P May, 08 23,500 Vacuum tower starts
Vernon to production mid-May,
Countrymark May, 08 raising capacity by 3,000
Cooperative Inc b/d. Fuel output to rise
Indiana, U.S. by 45 million gallons a
year, mostly diesel.Valero Wilmington P May 11, 08 135,000 Partial shutdown after
Valero Energy Corp to power failure.
California, U.S. May 18, 08Delek LaGloria U May 11, 08 58,000 FCC rates cut by boiler
Delek US Holdings Inc to failure. Restart
Texas, U.S. May 16, 08 confirmed.Shell Martinez U May 09, 08 165,000 Hydrocracker shuts for a
Royal Dutch Shell PLC to week.
California, U.S. May 16, 08Shell Canada Sarnia U May 08, 08 71,820 Runs cut as unit outage
Royal Dutch Shell PLC to curbed gasoline
Ontario, Canada May 17, 08 production. More specific
details not available.Hovensa St. Croix N May 08, 08 495,000 CDU shut for unscheduled
Petroleos de to repairs.
Venezuela SA, Hess May 16, 08
Corp
US Virgin Islands,
U.S.Navajo Artesia U May 07, 08 75,000 FCC shut after
Holly Corp to malfunction. Restart
New Mexico, U.S. May 24, 08 confirmed.Flint Hills Corpus P May 05, 08 300,000 Sulfur recovery unit No.
Christi to 2 shuts for maintenance.
Koch Industries Inc May 15, 08
Texas, U.S.Valero Corpus Christi P May 02, 08 38,000 CDU, Vaccum units shut
West to for two weeks as of May
Valero Energy Corp May 16, 08 2. Restart confirmed.
Texas, U.S.Holly Woods Cross N May 01, 08 26,000 Alkylation unit shut
Holly Corp to after fire. Restart
Utah, U.S. May 08, 08 confirmed.Total Port Arthur P Apr 30, 08 240,000 Sulfur recovery unit and
Total SA to units 804, 823, 824 and
Texas, U.S. May, 08 825 shut.BP Carson U Apr 28, 08 265,500 Hydrodesulfurization unit
BP PLC to breakdown. Restart
California, U.S. May 01, 08 confirmed.BP Texas City P Apr 25, 08 470,000 FCC No. 1, alkylation,
BP PLC to coker units shut.
Texas, U.S. May 28, 08Imperial Oil Sarnia U Apr 25, 08 121,000 Runs cut by boiler
Exxon Mobil Corp to failure and repair.
Ontario, Canada May, 08Murphy Superior P Apr 23, 08 35,000 Full shutdown to last
Murphy Oil Corp to about a month.
Wisconsin, U.S. May 25, 08Total Port Arthur U Apr 21, 08 240,000 Hydrotreater rates cut
Total SA to because of malfunction.
Texas, U.S. Apr, 08Alon Big Spring N Apr 19, 08 70,000 Sulfur recovery unit No.
Alon Israel Oil Co to 2 shut down.
Ltd Apr, 08
Texas, U.S.Flint Hills Corpus U Apr 18, 08 300,000 Sulfur recovery unit shut
Christi to for unplanned
Koch Industries Inc Apr, 08 maintenance.
Texas, U.S.Valero Norco St N Apr, 08 190,000 FCC runs cut amid
Charles to slumping margins.
Valero Energy Corp May, 08
Louisiana, U.S.BP Cherry Point P Apr 15, 08 232,000 Cokers, reformers shut
BP PLC to mid-April to mid-May in
Washington, U.S. May 19, 08 planned maintenance. Two
cokers and two reformers involved. Only one unit
will be down at a time. Reformer restart confirmed.Wynnewood OK P Apr, 08 70,000 Shutdown to expand
Gary-Williams Energy to capacity to 70,000
Co May 15, 08 barrels a day. Restart
Oklahoma, U.S. confirmed May 13.Shell Deer Park U Apr 14, 08 340,000 Coker, sulfur recovery
Royal Dutch Shell to unit faults reduce
PLC, Petroleos May 07, 08 refinery runs. Normal
Mexicanos operations estamated for
Texas, U.S. May 5.Conoco Rodeo N Apr 14, 08 76,000 Partial shutdown after
ConocoPhillips to unspecified malfunction.
California, U.S. Apr, 08 Conoco said production
not affected.Cenex Laurel P Apr 14, 08 55,000 Coker unit enters into
CHS Inc to production.
Montana, U.S. Apr 15, 08Exxon Mobil Torrance P Apr 12, 08 155,000 Alkylation unit shut for
Exxon Mobil Corp to planned maintenance.
California, U.S. Apr 30, 08Marathon Catlettsburg N Apr 11, 08 239,000 FCC shut after fire in
Marathon Oil Corp, to electrical substation.
Ashland Inc Apr 21, 08 Restart confirmed.
Kentucky, U.S.BP Carson N Apr 11, 08 265,500 Hydrocracker shut after
BP PLC to flash fire. Restart
California, U.S. Apr 14, 08 confirmed.Total Port Arthur P Apr 10, 08 240,000 Catalyst change to
Total SA to unspecified unit. Partial
Texas, U.S. Apr, 08 shutdown.ConocoPhillips Los P Apr 09, 08 147,000 CDU, hydrocracker, coker
Angeles to maintenance. Work to be
ConocoPhillips May 23, 08 completed in May,
California, U.S. ConocoPhillips said.Sunoco Marcus Hook N Apr 08, 08 175,000 Full shutdown after power
Sunoco Inc to failure. Resart sequence
Pennsylvania, U.S. Apr 10, 08 confirmed.Alon Big Spring N Apr 07, 08 70,000 CDU shut after fire in
Alon Israel Oil Co to tank farm. Restart
Ltd Apr 08, 08 confirmed.
Texas, U.S.Exxon Mobil Torrance N Apr 04, 08 155,000 Hydrotreater fire shuts
Exxon Mobil Corp to units. Unit restarted
California, U.S. Apr 06, 08 April 6.Valero Benicia U Apr 03, 08 153,000 Hydrocracker shut because
Valero Energy Corp to of leak. Restart
California, U.S. Apr 14, 08 confirmed.Valero Houston N Apr 01, 08 90,000 Alkylation unit shut
Valero Energy Corp to after substation fire.
Texas, U.S. Apr 02, 08 -