Update Jan 09 – Asian Paific Ref S/D & Project Table

Home Forums Coking Maintenance Shutdown/Turnaround Update Jan 09 – Asian Paific Ref S/D & Project Table

This topic contains 0 replies, has 1 voice, and was last updated by  Charles Randall 12 years, 5 months ago.

  • Author
    Posts
  • #3248

    Charles Randall
    Participant

    <Here is Bloomberg Update Jan 2009 of the Asia Pacific S/D & Project table – CER>
    ———
    Asian Oil Refinery Shutdowns, Maintenance, Expansion (Table)

    By Nesa Subrahmaniyan and Yuji Okada
         January 8, 2009 (Bloomberg)
    — The following is a table of refinery shutdowns in
    Asia, confirmed by Bloomberg. 

         Shutdown Type: P: Planned, U: Unplanned, N: Non-maintenance

    Refinery                           Shutdown  Capacity                          
    Company                  Period      Type      b/d     Unit Reason             
    ——————————————————————————–
                                   *** AUSTRALIA ***

    BP Kwinana               Oct 29, 08    P      138,000  CDU, FCC, alkylation,   
    BP PLC                     to                          sulfur recovery plant   
                             Dec 29, 08                    shut for repairs. Restart
                                                           confirmed.              

    Caltex Lytton            Qtr 1, 09     P      105,500  Full shutdown for full  
    Caltex Corp                to                          inspection and          
                             Qtr 2, 09                     maintenance in 2009 in  
                                                           four-five year cycle.   

                             Qtr 1, 09     P      105,500  New diesel hydrotreater 
                               to                          unit to start output in 
                             Qtr 1, 09                     first quarter 2009.     

                             Dec 12, 08    N      105,500  Full shutdown after steam
                               to                          loss. Units began restart
                             Jan 05, 09                    on 12/13. Full production
                                                           planned for early       
                                                           January.                

                             Qtr 3, 08     P      105,500  CDU, diesel hydrotreater
                               to                          shut for maintenance in 
                             Qtr 4, 08                     second half of year.    

    Shell Clyde              Nov 30, 08    P       86,000  Full shutdown starting  
    Royal Dutch Shell PLC      to                          end Nov.                
                             N/A                                                   

                                     *** CHINA ***

    CNOOC Huizhou            Qtr 1, 09     P      240,000  New refinery planned to 
    China National Offshore    to                          come on line in 2009.   
    Oil Corp                 Qtr 2, 09                                             

    PetroChina Dushanzi      Aug, 08       P      120,000  Capacity to increase to 
    China National             to                          10 million tons from 6  
    Petroleum Corp           Aug, 08                       million tons a year, with
                                                           the additional capacity 
                                                           scheduled to start in   
                                                           August.                 

    PetroChina Fushun        Oct 10, 08    P      162,000  New CDU, capacity 160,000
    China National             to                          barrels a day, begins   
    Petroleum Corp           Oct, 08                       trial production.       

    Petrochina Lanzhou       Aug 23, 08    P      151,800  CDU, FCC shuts for      
    China National             to                          planned repairs, from   
    Petroleum Corp           Sep 29, 08                    Aug. 23 for 30 to 45    
                                                           days.                   

    Sinopec Hainan           Qtr 4, 09     P      128,700  Full shutdown of the    
    China Petrochemical        to                          160,000 b/d refinery for
    Corp                     Qtr 4, 09                     30 days in 4Q of 2009.  

                             Dec 31, 08    P      128,700  Hydrocracker, capacity  
                               to                          24,000 b/d, shuts for   
                             Feb 15, 09                    maintenance.            

    Sinopec Maoming          Oct, 09       P      270,000  New wax hydrotreater    
    China Petrochemical        to                          scheduled to begin      
    Corp                     Oct, 09                       operations. Capacity    
                                                           36,000 barrels a day.   

    Sinopec Qilu             Jul 31, 08    P      210,000  CDU                     
    China Petrochemical        to                                                  
    Corp                     Aug 28, 08                                            

    Sinopec Tianjin          Qtr 1, 09     P      100,000  New units to increase   
    China Petrochemical        to                          crude distillation      
    Corp                     Qtr 4, 09                     capacity to 250,000     
                                                           barrels a day scheduled 
                                                           to start in 2009.       

                             Sep 05, 08    P      100,000  100,000 b/d CDU shut for
                               to                          maintenance.            
                             Nov 06, 08                                            

                                     *** INDIA ***

    Indian Gujarat Koyali    Qtr 1, 10     P      274,000  New diesel hydrotreater 
    Indian Oil Corp Ltd        to                          unit to start.          
                             Qtr 2, 10                                             

                             Aug, 08       P      274,000  CDU. 3.8                
                               to                          million-tons-a-year     
                             Sep, 08                       (77,000 barrels-a-day)  

                             Aug, 08       P      274,000  FCC, 1.5                
                               to                          million-metric-tons-a-yea
                             Sep, 08                       (30,400 barrels-a-day)  
                                                           shuts for maintenance.  

                             Aug, 08       P      274,000  Diesel desulfurization  
                               to                          unit. 1.44              
                             Sep, 08                       million-tons-a-year     
                                                           (30,000 barrels-a-day)  

    Indian Mathura           Aug 25, 08    P      160,000  Hydrotreater shuts for  
    Indian Oil Corp Ltd        to                          maintenance.            
                             Sep, 08                                               

    Indian Panipat           Sep 14, 08    P      120,000  Half the capacity will be
    Indian Oil Corp Ltd        to                          closed.                 
                             Oct 05, 08                                            

    MRPL Mangalore           Oct 02, 11    P      193,800  New Units to expand     
    Oil & Natural Gas Corp     to                          capacity to 15 million  
    Ltd                      Oct 31, 11                    metric tons a year.     

                             Oct 18, 08    P      193,800  CDU, hydrocracker shut  
                               to                          for maintenance.        
                             Nov 10, 08                                            

    Reliance Jamnagar        Dec 25, 08    P      660,000  New units commission to 
    Reliance Industries Ltd    to                          increase capacity by    
                             Dec 25, 08                    580,000 barrels a day to
                                                           1.24 million barrels a  
                                                           day.                    

                                   *** INDONESIA ***

    Pertamina Balongan       Oct 15, 08    P      125,000  Full shutdown for 57 days
    Pertamina PT               to                          from mid-October. Restart
                             Jan 09, 09                    in mid December failed, 
                                                           full restart postponed to
                                                           Jan. 9.                 

    Pertamina Cilacap        Mar, 09       P      348,000  230,000 b/d No. 2 CDU   
    Pertamina PT               to                          shuts for maintenance.  
                             Apr, 09                                               

                             Aug, 08       P      348,000  Runs cut by 34%, or     
                               to                          118,000 barrels a day,  
                             Aug 27, 08                    for August maintenance. 

    Pertamina Dumai          Dec 15, 08    U      150,000  Runs cut 15% because of 
    Pertamina PT               to                          fire in tank farm.      
                             Dec 17, 08                                            

    Pertamina Plaju          Mar, 09       P      120,200  CDU shutdown to cut     
    Pertamina PT               to                          refinery output by 25,000
                             Mar, 09                       barrels a day.          

                                     *** JAPAN ***

    Cosmo Chiba              Sep 13, 08    P      240,000  CDU No. 1 restarted Nov.
    Cosmo Oil Co Ltd           to                          10                      
                             Nov 09, 08                                            

    Cosmo Sakai              Aug 22, 08    P       80,000  CDU No. 1 shuts         
    Cosmo Oil Co Ltd           to                                                  
                             Sep 30, 08                                            

    Cosmo Yokkaichi          Sep 28, 08    P      175,000  90,000 b/d CDU No. 5    
    Cosmo Oil Co Ltd           to                          shuts. Restart confirmed.
                             Nov 22, 08                                            

    Idemitsu Aichi           Oct, 09       P      160,000  CDU No. 1, capacity     
    Idemitsu Kosan Co Ltd      to                          160,00 b/d, shuts for   
                             Nov, 09                       maintenance.            

                             Oct 23, 08    P      160,000  RFCC, capacity 60,000   
                               to                          b/d, shuts for          
                             Nov 20, 08                    maintenance.            

                             Jul 03, 08    U      160,000  RFCC shuts for          
                               to                          maintenance.            
                             Jul 17, 09                                            

    Idemitsu Chiba           Apr, 09       P      220,000  CDU No. 2, capacity     
    Idemitsu Kosan Co Ltd      to                          220,000 b/d, shuts for  
                             May, 09                       maintenance.            

    Idemitsu Hokkaido        Jun, 09       P      140,000  CDU No. 1, capacity     
    Idemitsu Kosan Co Ltd      to                          140,000 b/d, shuts for  
                             Jul, 09                       maintenance.            

    Japan Kashima            Sep 05, 08    P      270,000  60,000 barrels a day    
    Nippon Mining Holdings     to                          condensate splitter     
    Inc                      Oct 15, 08                                            

                             Aug 26, 08    U      270,000  CDU shuts because of    
                               to                          operating fault.        
                             Aug 31, 08                                            

                             Jul 10, 08    U      270,000  FCC, capacity 35,500 b/d,
                               to                          shuts for repairs.      
                             Jul 22, 08                    Restart confirmed.      

    Japan Mizushima          Mar, 09       P      205,200  CDU No. 2, capacity     
    Nippon Mining Holdings     to                          95,200 barrels-a-day,   
    Inc                      May, 09                       shuts for maintenance.  

    Japan Sodegaura          May, 09       P      192,000  CDU No. 2, capacity     
    AOC Holdings Inc           to                          140,000 b/d, and all    
                             Jun 20, 09                    secondary units shut for
                                                           maintenance.            

    Nansei Nishihara         May, 09       P      100,000  100,000 b/d No. 1 CDU   
    Petroleo Brasileiro SA,    to                                                  
    Sumitomo Corp            May, 09                                               

    Nippon Mizushima         Nov 14, 08    N      250,000  CDU No. 2, capacity     
    Nippon Oil Corp            to                          110,000 barrels a day,  
                             Dec 09, 08                    shuts on Nov. 14 on     
                                                           slowing oil demand.     

                             Sep 08, 08    P      250,000  140,000 barrels-a-day No.
                               to                          3 CDU shuts             
                             Sep 30, 08                                            

    Nippon Negishi           Oct 01, 08    P      340,000  150,000 b/d CDU         
    Nippon Oil Corp            to                                                  
                             Oct 18, 08                                            

    Nippon Osaka             Mar, 09       P      115,000  CDU No. 1, capacity     
    Nippon Oil Corp            to                          115,000 b/d, shuts for  
                             Apr, 09                       repairs.                

    Showa Yamaguchi          Sep 01, 08    P      120,000  120,000 barrels a day CDU
    Showa Shell Sekiyu KK      to                          No. 2 shuts             
                             Oct 06, 08                                            

    Showa Yokkaichi          May, 09       P      210,000  CDU No. 3, capacity     
    Showa Shell Sekiyu KK      to                          135,000 b/d, shuts for  
                             Jul, 09                       repairs.                

    Taiyo Shikoku            Sep 01, 08    N      120,000  Full shutdown after power
    Taiyo Oil Co               to                          cut.                    
                             Sep 02, 08                                            

    Teikoku Kubiki           Nov, 09       P        4,724  4,724 b/d CDU shut      
    Teikoku Oil Co Ltd         to                                                  
                             Nov, 09                                               

                             May, 09       P        4,724  4,724 b/d CDU shut.     
                               to                                                  
                             Jun, 09                                               

    Toa Keihin               Apr, 09       P      185,000  65,000 b/d No. 3 CDU    
    Toa Oil Co Ltd             to                                                  
                             May, 09                                               

    TonenGeneral Kawasaki    Sep 07, 08    U      335,000  Runs cut because of power
    TonenGeneral Sekiyu KK     to                          failure.                
                             Sep, 08                                               

    TonenGeneral Sakai       Jul 01, 08    N      156,000  CDU shuts after fire.   
    TonenGeneral Sekiyu KK     to                          Restart confirmed.      
                             Jul 04, 09                                            

    TonenGeneral Wakayama    Oct 02, 08    P      170,000  CDU No. 3               
    TonenGeneral Sekiyu KK     to                                                  
                             Oct 30, 08                                            

                             Sep 22, 08    P      170,000  CDU No. 2               
                               to                                                  
                             Sep 27, 08                                            

                             Jul 08, 08    N      170,000  Shutdown after power cut.
                               to                                                  
                             Jul 09, 08                                            

                                  *** NEW ZEALAND ***

    New Zealand Whangarei    Sep, 09       P      109,000  New units to expand crude
    BP Oil New Zealand Ltd,    to                          distillation capacity by
    Mobil Oil New Zealand    Sep, 09                       35,000 b/d, to 95,000   
    Ltd, Shell New Zealand                                 b/d, scheduled to start 
    Holdings Co Ltd,                                       in September 2009.      
    Emerald Capital                                                                
    Holdings Inc, Caltex                                                           
    New Zealand Ltd                                                                

                             Feb, 09       P      109,000  Platformer catalyst     
                               to                          change planned for      
                             Feb, 09                       February 2009. Delayed  
                                                           from November 2008.     

                                    *** PAKISTAN ***

    National Karachi         Nov 04, 08    U       62,500  Full shutdown for       
    Attock Oil Group of Cos    to                          unscheduled repairs.    
                             Nov 14, 08                                            

                                  *** PHILIPPINES ***

    Petron Bataan            Dec 01, 08    P      180,000  Full shutdown for one   
    Petron Corp                to                          month starting in       
                             Jan 01, 09                    December to tie in new  
                                                           Benzene, Toulene, Xylene
                                                           unit.                   

                                  *** SOUTH KOREA ***

    GS-Caltex Yosu           Qtr 1, 10     P      650,000  New Hydrocracker No. 3 to
    LG Group, Chevron Corp     to                          come on line in 2010.   
                             Qtr 4, 10                                             

                             Oct 13, 08    U      650,000  130,000 b/d CDU No. 2   
                               to                          shuts because of flash  
                             Oct 14, 08                    fire.                   

    Inchon Inchon            Jun, 11       P      275,000  New Hydrocracker 40,000 
    SK Energy Co Ltd           to                          barrels/day construction
                             Jun, 11                       to start June 2008 and  
                                                           operations scheduled to 
                                                           start June 2011
            

    SK Ulsan                 Oct 06, 08    P      840,000  Hydrocracker            
    SK Energy Co Ltd           to                                                  
                             Oct 17, 08                                            

                             Sep 22, 08    P      840,000  Middle Distillation Unit
                               to                          No. 3 shuts.            
                             Oct 08, 08                                            

                                     *** TAIWAN ***

    CPC Kaohsiung            Oct 15, 08    P      220,000  CDU No. 8, 100,000 b/d  
    CPC Corp Taiwan            to                          capacity, shut for      
                             Dec 09, 08                    maintenance for more than
                                                           40 days, restarted in   
                                                           early December. Residue 
                                                           desulfurization also  
      
                                                           restarted.              

    Formosa Mailiao          Mar, 09       P      540,000  Residue desulfurization 
    Formosa Petrochemical      to                          unit, capacity 80,000   
    Corp                     Apr, 09                       b/d, will be shut for 40
                                                           days.                   

                             Nov 20, 08    P      540,000  CDU, capacity 180,000,  
                               to                          vacuum distillation unit,
                             Dec, 08                       delayed coker shut until
                                                           the end of December.    

                             Sep 01, 08    P      540,000  80,000 b/d residue      
                               to                          desulfurization unit.   
                             Oct 18, 08                                            

                             Jul 15, 08    U      540,000  RFCC, capacity 84,00    
                               to                          barrels a day, shuts for
                             Jul 31, 08                    leaking boiler.         

                             Jul 01, 08    U      540,000  RFCC shuts July 1 for   
                               to                          10-15 days because of   
                             Jul 13, 08                    boiler leak.            

                                    *** THAILAND ***

    Bangchak Bangkok         Dec, 08       P      120,000  One week shutdown in    
    PTT PCL, Krung Thai        to                          December for maintenance.
    Bank PCL                 Dec, 08                                               

                             Aug 22, 08    U      120,000  CDU shuts after leak.   
                               to                                                  
                             Sep, 08                                               

    Rayong Sri Racha         Aug 18, 08    P      145,000  Full shutdown for repairs
    Alliance Refining Co       to                          and inspection.         
                             Aug 31, 08                                            

                                    *** VIET NAM ***

    Dung Quat                Feb, 09       P      145,000  New refinery to begin   
    PetroVietnam               to                          production in February  
                             Feb, 09                       2009.                   

    –Editor: Clyde Russell.