Table Of Asia Refinery Maintenance/Shutdown Schedules
SINGAPORE -(Dow Jones)- The following table lists recent and upcoming maintenance schedules and outages for oil refineries in Asia. More information will be added as it becomes available. Country Company Location Unit(B/D) Period/Duration
Australia BP Kwinana part of refinery Sep 30; 1 week
(137,000)
China PetroChina Qianguo Whole Refinery Permanent
China Wepec Dalian RFCC End Sep; 2 weeks
(3 million*)
India CPCL Chennai Third of Refinery Jan-Feb; 50 days
(65,000)
India MRPL DHDS Feb/Mar 2010; 30 days
(24,000)
India IOC Panipat CDU July-Aug 2010; 40-45 days (120,000)
India HPCL Vizag FCC Nov/Dec; 45 days
(14,000)
India HPCL Vizag HDS Dec-Jan; 30 days
(45,000)
Indonesia Pertamina Balikpapan CDU Oct; 20-25 days
(60,000)
Hydrocracker Mid-Jan; Indefinitely
(15,000)
Indonesia Pertamina Plaju CDU Dec; 2 days
(30,000)
Indonesia Pertamina Balongan Whole Refinery Late January; 10 days
(150,000)
Indonesia Pertamina Balongan RFCC During Week Of Jan 11-17 (NA)
Indonesia Pertamina Plaju Whole Refinery Late Jan
(118,000)
Japan Nippon Oil Marifu CDU Feb 2010; 1 Month
(127,000)
Japan Nippon Oil Mizushima No. 2 CDU Mid Jul-End March 2010
(110,000)
Japan Taiyo Oil Shikoku No. 1 & 2 CDU Mid Jun, 2010; 2 Months
(120,000)
Singapore Shell Bukom Hydrocracker Mid Sep; 2 months
(34,000)
S Korea S-Oil Onsan No. 2 RHDS Oct 5-31
(53,000)
S Korea S-Oil Onsan No. 3 CDU March 2010; 22 days
(250,000)
S Korea S-Oil Onsan No. 1 VRDS March 2010; 30 days
(52,000)
S Korea S-Oil Onsan hydrocracker March 2010; 30 days
(75,000)
S Korea S-Oil Onsan RFCC June 2010; 30 days
(73,000)
S Korea SK Energy Ulsan No. 1 CDU Early Apr-TBA
(60,000)
S Korea SK Energy Ulsan No. 2 RFCC July (1 month)
(60,000)
S Korea GS Caltex Yeosu No. 1 CDU Apr 2010; 30 days
(100,000)
S Korea Hyundai Oilbank Daesan No. 2 CDU Apr 2010; 20 days
(290,000)
Taiwan CPC Dalin No. 9 CDU Sep 1-End Feb
(100,000)
Taiwan CPC Dalin No. 1 RDS Dec 10-Feb 2
(30,000)
Taiwan CPC Dalin No. 6 Reformer Aug 3-Nov 3
(30,000)
Taiwan CPC Taoyuan No. 2 CDU Dec 19-Jan 24
(100,000)
Taiwan CPC Taoyuan No. 2 Reformer Dec 10; 60 days
(25,000)
Taiwan CPC Taoyuan VGH Aug 31-Nov 30
(20,000)
Taiwan CPC Taoyuan RFCC Nov 1-Jan 10
(50,000)
Taiwan CPC Kaohsiung FCC Oct-Feb
(25,000)
Taiwan CPC Kaohsiung No. 2 RDS From March 8 (38-40 days) (30,000)
Taiwan Formosa Mailiao No. 1 RFCC Oct 8-Nov 14 ’09
(84,000)
Taiwan Formosa Mailiao No. 2 RFCC Oct 1-10 ’09
(84,000) From Mar 2010 (55-60 days)Taiwan Formosa Mailiao No. 1 RDS Oct 1-Nov 2 ’09
(80,000) From Mar 2010 (35 days)
Taiwan Formosa Mailiao No. 2 RDS Oct 1-Nov 2 ’09
(80,000) Oct 2010
Taiwan Formosa Mailiao No. 1 CDU Mar 21-31 ’10
(180,000)
Taiwan Formosa Mailiao No. 2 CDU Sep 23-25 ’09
(180,000) Oct 1-Nov 5 ’09
Taiwan Formosa Mailiao No. 3 CDU Mar 1-21 ’10
(180,000)
Taiwan Formosa Mailiao Delayed Coker Dec 4-18 ’09
(36,000)
Vietnam PetroVietnam Dung Quat whole refinery Aug 18-Oct 1
(130,000) Dec 22-Jan 13Note: B/D – Barrels a day
N/A – Not available
TBA – To be announced
CDU – Crude distillation unit
FCC – Fluid catalytic cracker
HDS – Hydrodesulfurizer
RCC – Residue catalytic cracker
RFCC – Residual fluid catalytic cracker
RDS – Residual desulfurizer
RHDS – Residue hydro desulfurizer
VRDS – Vacuum residual desulfurizer * – Tons a yearKeyword search “Table Of Asia Refinery Maintenance” for details of previous refinery outages. (END) Dow Jones Newswires