Turnaround Best Practices

Home Forums Conferences 2012 Texas Turnaround Best Practices

This topic contains 0 replies, has 1 voice, and was last updated by  4 drums coker 8 years, 6 months ago.

  • Author
    Posts
  • #1866

    4 drums coker
    Participant

    Facilitators – Paul Komperda, United Laboratories & Jim Merrill, AltairStrickland

    T/A BEST PRACTICES

    Start Planning?
    18-24 months – T/A Group
    4-8 months – Build work scope

    Factors:
    – Equipment lead time
    – Workscope (finalize 3-4 mos. before)
    – Mobilization

    T/A MGT

    – Capital Group
    – S/D oil out Process
    – Manpower loading
    – Discovery Work

    1. T/A TEAM PLAN SCOPE

    2. PREPLAN INSPECTIONS AT COMMON TROUBLE AREA

    3. BUILD CONTRACTOR/PLANT TEAM