    North American Planned, Unplanned Refinery Shutdowns (Table)

    By Robert Tuttle
         July 14, 2008 (Bloomberg) — Following is a table of scheduled and unplanned
    refinery shutdowns, maintenance, new plants and capacity expansions in North
    America. The list only includes work that could be confirmed. 

         Shutdown Type: P: Planned, U: Unplanned, N: Non-maintenance

    Refinery                                     Refinery                          
    Owner                  Shutdown              Capacity                          
    Location                 Type    Period        b/d     Notes                   

    ——————————————————————————–
    New Information:

    Valero Ardmore             U     Jul 08, 08    85,000  FCCU shut after power   
    Valero Energy Corp                 to                  disruption, restart     
    Oklahoma, U.S.                   Jul 11, 08            confirmed.              

    Current Outages:

    Petro-Canada Edmonton      U     Jul 09, 08   135,000  Full shutdown after     
    Petro-Canada                       to                  boiler failure. No      
    Alberta, Canada                  N/A                   timeframe for restart.  

    Alon Big Spring            N     Feb 18, 08    70,000  Full shutdown by an     
    Alon Israel Oil Co                 to                  explosion in the propylene unit.       
    Ltd                              Aug 15, 08            The refinery processing 35,000     
    Texas, U.S.                                            bbl/day as of April 7. FCCU expected to
                                                           resume service in August, alkylation unit two weeks
                                                           later.                  

    Future Outages:

    Frontier El Dorado         P     Aug, 08      112,000  New coker to start      
    Frontier Oil Corp                  to                  operations in August,   
    Kansas, U.S.                     Aug, 08               capacity 3,000 barrels a
                                                           day.                    

    Holly Woods Cross          P     Aug, 08       26,000  Turnaround planned.     
    Holly Corp                         to                                          
    Utah, U.S.                       Sep, 08                                       

    Sunoco Toledo              P     Qtr 3, 08    150,000  CDU, FCC units to shut in
    Sunoco Inc                         to                  third quarter           
    Ohio, U.S.                       Qtr 3, 08             maintenance.            

    Petro-Canada Edmonton      P     Qtr 3, 08    135,000  Full shutdown of 135,000
    Petro-Canada                       to                  bbl/day refinery during 
    Alberta, Canada                  Qtr 4, 08             the second half 2008 to 
                                                           allow new units to be added to the plant as   
                                                           part of an upgrade.     

    PEMEX Hidalgo Tula         P     Sep, 08      273,000  FCC shuts for planned   
    Petroleos Mexicanos                to                  maintenance of up to 90 days.
    Mexico                           Dec, 08                                  

    Conoco Wood River          P     Qtr 3, 08    306,000  Catalytic cracker       
    EnCana Corp,                       to                  maintenance to install  
    ConocoPhillips                   Qtr 4, 08             wet-gas scrubbers to    
    Illinois, U.S.                                         reduce emissions.       

    Paramount                  P     Qtr 4, 08     55,000  Hydrocracker startup to 
    Alon USA Energy Inc                to                  increase gasoline, diesel
    California, U.S.                 Qtr 4, 08             output by 50 percent.   

    Holly Woods Cross          P     Qtr 4, 08     26,000  Hydrocracker, capacity  
    Holly Corp                         to                  15,000 barrels a day,   
    Utah, U.S.                       Qtr 4, 08             planned to start production. Crude       
                                                           refining capacity to rise to 31,000 barrels a day.

    Valero Delaware City       P     Qtr 4, 08    190,200  CDU, capacity 180,000   
    Valero Energy Corp                 to                  b/d, shuts for          
    Delaware, U.S.                   Qtr 4, 08             maintenance.            

    Motiva Norco               P     Oct 03, 08   220,000  FCC, capacity 110,000   
    Saudi Arabian Oil Co,              to                  barrel-a-day, shuts for 
    Royal Dutch Shell PLC            Nov 10, 08            maintenance.            
    Louisiana, U.S.                                                                

    Conoco Wood River          P     Qtr 1, 09    306,000  New Coker, 65,000 b/d   
    EnCana Corp,                       to                  capacity, scheduled to  
    ConocoPhillips                   Qtr 4, 09             come on stream in 2009. 
    Illinois, U.S.                                                                 

    Navajo Artesia             P     Jan, 09       75,000  New hydrocracker,       
    Holly Corp                         to                  capacity 15,000 barrels a
    New Mexico, U.S.                 Jan, 09               day, expected to start  
                                                           production. Turnaround planned.                

    Valero Krotz Springs       P     Qtr 1, 09     83,100  Full turnaround planned 
    Alon USA Energy Inc                to                  for 2009.               
    Louisiana, U.S.                  Qtr 4, 09                                     

    Valero Benicia             P     Qtr 1, 09    153,000  Full shutdown scheduled 
    Valero Energy Corp                 to                  for 2009 in five-year   
    California, U.S.                 Qtr 4, 09             cycle of maintenance.   

    Conoco Borger              P     Qtr 1, 09    146,000  New capacity,           
    ConocoPhillips,                    to                  debottlenecking to add  
    EnCana Corp                      Qtr 4, 09             20,000 b/d bitumen      
    Texas, U.S.                                            capacity.               

    Sunoco Philadelphia        P     Qtr 1, 09    330,000  New Hydrocracker        
    Sunoco Inc                         to                  conversion project to start  
    Pennsylvania, U.S.               Qtr 4, 09       operations in 2009, upgrading
                                                                 45,000 b/d of product into ultra-low   
                                                                  sulfur diesel.          

    PEMEX Cardenas             P     Feb 02, 09   190,000  New units to expand     
    Minatitlan                         to                         capacity to 260,000 b/d 
    Petroleos Mexicanos              Feb 28, 09       scheduled to start in  February 2009 
    Mexico                                                          

    Giant Yorktown             P     Qtr 3, 09     61,900  Turnaround scheduled for
    Giant Industries Inc               to                  late 2009, no more      
    Virginia, U.S.                   Qtr 4, 09             specific details available.                      

    Marathon Garyville         P     Qtr 4, 09    275,000  New CDU, VDU,           
    Marathon Oil Corp,                 to                  hydrocracker (capacity  
    Ashland Inc                      Qtr 4, 09             70,000 b/d), delayed    
    Louisiana, U.S.                                        coker (44,000 b/d), reformer (65,000 b/d),  
                                                           kerosene hydrotreater (47,000) planned to come
                                                           on line, raising refinery throughput to 425,000   
                                                           barrels a day.          

    Valero Benicia             P     Qtr 1, 10    153,000  New units to expand CDU 
    Valero Energy Corp                 to                  capacity 25% to daily   
    California, U.S.                 Qtr 4, 10             runs of 180,000 b/d,    
                                                           coker by 25%, SRU by 50% to handle
                                                           heavier crudes, reduce gasoil imports and
                                                           expand gasoline output. 

    Chevron Richmond           P     Qtr 1, 10    257,200  New Hydrogen plant,     
    Chevron Corp                       to                  reforming units to improve     
    California, U.S.                 Qtr 4, 10           crude feedstock flexibility scheduled to
                                                           start in 2010. No change to refinery capacity.   

    Motiva Port Arthur         P     Qtr 1, 10    285,000  New units to add 325,000
    Motiva Enterprises                 to                  b/d crude capacity, to  
    LLC                              Qtr 4, 10             start in 2010.          
    Texas, U.S.                                                                    

    Pasadena                   P     Qtr 1, 10    106,500  New units to double     
    Nationale A                        to                  capacity to 200,000     
    Portefeuille                     Qtr 4, 10             barrels a day planned to
    Texas, U.S.                                            start in 2010.          

    Valero Norco St            P     Qtr 1, 10    190,000  New Hydrocracker planned
    Charles                            to                  to enter service in 2010.
    Valero Energy Corp               Qtr 4, 10                                     
    Louisiana, U.S.                                                                

    Marathon Detroit           P     Qtr 4, 10    100,000  New Coker, capacity     
    Marathon Oil Corp,                 to                  28,000 b/d, scheduled to
    Ashland Inc                      Qtr 4, 10             enter service, along with
    Michigan, U.S.                                         sulfur recovery unit (280
                                                           long tons/day), distillate hydrotreater 
                                                           (33,000 b/d) and hydrogen plant. Nameplate capacity
                                                           of refinery to increase to 115,000 b/d.         

    Sinclair Tulsa             P     Qtr 4, 10     60,000  New CDU, hydrocracker,  
    Sinclair Oil Corp                  to                  coker units planned to start 
    Oklahoma, U.S.                   Qtr 4, 10        operations. Capacity to increase to 
                                                           115,000 barrels a day.  

    Valero Port Arthur         P     Qtr 4, 10    325,000  New Hydrocracker        
    Valero Energy Corp                 to                  construction to be      
    Texas, U.S.                      Qtr 4, 10             completed, capacity     
                                                           50,000 barrels a day, to
                                                           start in 4Q 2010.       

    Total Port Arthur          P     Qtr 1, 11    240,000  New Coker (50,000 b/d), 
    Total SA                           to                  desulfurization and vacuum    
    Texas, U.S.                      Qtr 4, 11        distillation unit.The $2.2 billion project
                                                           is scheduled to be completed in 2011.      

    BP Whiting                 P     Qtr 1, 11    420,000  New Coker, capacity     
    BP PLC                             to                  120,000 b/d, along with related
    Indiana, U.S.                    Qtr 4, 11          units to process Canadian heavy oil      
                                                           scheduled to begin service in 2011.        

    Valero Port Arthur         P     Qtr 2, 11    325,000  New Coker construction to
    Valero Energy Corp                 to              be completed, capacity 45,000 
    Texas, U.S.                      Qtr 2, 11          barrels a day, during 2Q of 2011.      
                                                           Refinery throughput to rise to 415,000 b/d in  
                                                           conjunction with related investments.            

    Consumers’ Co-op           P     Jan, 12      100,000  New CDU expansion to add
    Regina                             to                  30,000 b/d capacity to a
    Federated                        Dec, 12               total 130,000 b/d, also 
    Co-operative Ltd                                       add FCC complex, planned
    Saskatchewan, Canada                             to start operations in 2012.                    

    Valero Quebec City         P     Qtr 1, 12    215,000  New Hydrocracker,       
    Valero Energy Corp                 to                  de-asphalting units     
    Quebec, Canada                   Qtr 4, 12             planned for 2012 startup.

    Conoco Borger              P     Qtr 1, 12    146,000  New units to expand crude
    ConocoPhillips,                    to                  distillation to 200,000 
    EnCana Corp                      Qtr 4, 12             b/d, with 75,000 b/d    
    Texas, U.S.                                            bitumen capacity.       

    Historical Outages:

    Total Port Arthur          P     Jul 09, 08   240,000  Hydrotreater and eight  
    Total SA                           to                  other units shut.       
    Texas, U.S.                      Jul 13, 08                                    

    Valero Ardmore             U     Jul 08, 08    85,000  FCCU shut after power   
    Valero Energy Corp                 to                  disruption, restart     
    Oklahoma, U.S.                   Jul 11, 08            confirmed.              

    Tesoro Martinez            U     Jul 08, 08   166,000  Gasoil hydrotreater shuts
    Tesoro Corp                        to                  because of leaking valve.
    California, U.S.                 Jul 09, 08            Restart confirmed.      

    US Oil Tacoma              N     Jul 07, 08    35,000  Runs cut 50% after power
    Nationale A                        to                  failure.                
    Portefeuille                     Jul, 08                                       
    Washington, U.S.                                                               

    BP Texas City                 Jul 01, 08   470,000  Flaring Reported During 
    BP PLC                             to                  residual hydrotreater   
    Texas, U.S.                      Jul 01, 08            startup.                

    Total Port Arthur          P     Jun 25, 08   240,000  CDU No. 2 shuts for     
    Total SA                           to                  maintenance.            
    Texas, U.S.                      Jul, 08                                       

    Lake Charles               N     Jun 25, 08   320,000  Units shut by power cut 
    Petroleos de                       to                  June 25. Operations     
    Venezuela SA                     Jun, 08               restarted the same day. 
    Louisiana, U.S.                                                                

    Valero Corpus Christi      P     Jun 23, 08    38,000  Refinery cut production 
    West                               to                  rates at the fluid catalytic cracking     
    Valero Energy Corp               Jun 23, 08    unit at Corpus Christi plant after 
    Texas, U.S.                                          after a steam leak caused excess
                                                              emissions. Output was not reduced.        

    BP Texas City              U     Jun 22, 08   470,000  FCC No. 1 pump leaks.   
    BP PLC                             to                  Effect on output not    
    Texas, U.S.                      Jun, 08               disclosed.              

    Exxon Mobil Baytown        N     Jun 22, 08   563,000  Sulfur recovery unit    
    Exxon Mobil Corp                   to                  shuts. All customer needs
    Texas, U.S.                      Jun, 08               being met, Exxon said.  

    BP Carson                  N     Jun 21, 08   265,500  CDU shuts after power   
    BP PLC                             to                  outage. Unit was in     
    California, U.S.                 Jun 23, 08            restart June 23.        

    Conoco Ponca City          N     Jun 20, 08   187,000  FCC shuts after power   
    ConocoPhillips                     to                  cut. Restart confirmed. 
    Oklahoma, U.S.                   Jun 22, 08                                    

    Shell Deer Park            U     Jun 18, 08   340,000  FCC wet gas compressor  
    Royal Dutch Shell                  to                  trips.                  
    PLC, Petroleos                   Jun 19, 08                                    
    Mexicanos                                                                      
    Texas, U.S.                                                                    

    Delek LaGloria             N     Jun 18, 08    58,000  CDU, alkylation shut by 
    Delek US Holdings Inc              to                  power failure. Units    
    Texas, U.S.                      Jun 19, 08            restarted.              

    Exxon Mobil Torrance       P     Jun 13, 08   155,000  Sulfur recovery unit    
    Exxon Mobil Corp                   to                  shuts for maintenance.  
    California, U.S.                 Jun 30, 08            Restart confirmed.      

    Pasadena                   P     Jun 11, 08   106,500  FCC unit upset. No      
    Nationale A                        to                  additional details      
    Portefeuille                     Jun, 08               available.              
    Texas, U.S.                                                                    

    LyondellBasell             N     Jun 10, 08   287,000  CDU shut during storm.  
    Houston                            to                  Restart confirmed.      
    Lyondell Chemical Co             Jun 11, 08                                    
    Texas, U.S.                                                                    

    Shell Deer Park            N     Jun 10, 08   340,000  FCC shuts in brief outage
    Royal Dutch Shell                  to                  after compressor fails
    PLC, Petroleos                   Jun 11, 08                                    
    Mexicanos                                                                      
    Texas, U.S.                                                                    

    Delek LaGloria             N     Jun 10, 08    58,000  Power failure shuts     
    Delek US Holdings Inc              to                  unspecified units.      
    Texas, U.S.                      Jun 11, 08            Operations restarted.   
                                                           Production loss not     
                                                           specified.              

    Valero Port Arthur         P     Jun 08, 08   325,000  distillate hydrotreater 
    Valero Energy Corp                 to                  shuts for maintenance.  
    Texas, U.S.                      Jun 12, 08                                    

    Valero Wilmington          U     Jun 06, 08   135,000  FCC, alkylation shut by 
    Valero Energy Corp                 to                  leak. Restart confirmed.
    California, U.S.                 Jun 09, 08                                    

    Conoco Borger              P     Jun 06, 08   146,000  FCC shut for repairs.   
    ConocoPhillips,                    to                                          
    EnCana Corp                      Jun 09, 08                                    
    Texas, U.S.                                                                    

    ConocoPhillips             U     Jun 03, 08   247,000  FCC shuts for repairs.  
    Alliance                           to                  Restart confirmed.      
    ConocoPhillips                   Jun 18, 08                                    
    Louisiana, U.S.                                                                

    Valero Delaware City       U     Jun 03, 08   190,200  Coker rates cut because 
    Valero Energy Corp                 to                  of boiler fault. Restart
    Delaware, U.S.                   Jun 06, 08            confirmed.              

    Sunoco Marcus Hook         U     Jun, 08      175,000  FCC runs cut by         
    Sunoco Inc                         to                  operational upset. Full 
    Pennsylvania, U.S.               Jun 27, 08     rates scheduled for the end of June.             

    Motiva Port Arthur         N     Jun 02, 08   285,000  Full shutdown after power
    Motiva Enterprises                 to                  cut. Restart began June 5.
    LLC                              Jun 05, 08                                 
    Texas, U.S.                                                                    

    BP Texas City              P     May 31, 08   470,000  Hydrocracker            
    BP PLC                             to                  (ultracracker) shuts.   
    Texas, U.S.                      Jun 05, 08            Additional details not  
                                                           available.              

    Motiva Norco               P     May 30, 08   220,000  Hydrocracker shuts for  
    Saudi Arabian Oil Co,              to                  mainteance late May for a
    Royal Dutch Shell PLC            Jul 09, 08            month. Restart confirmed.
    Louisiana, U.S.                                                                

    Big West Oil               U     May 30, 08    68,000  Sulfur recovery unit    
    Bakersfield                        to                  shuts.                  
    Flying J Oil & Gas               May 30, 08                                    
    Inc                                                                            
    California, U.S.                                                               

    BP Carson                  P     May 29, 08   265,500  Coker shuts for         
    BP PLC                             to                  maintenance. Restart    
    California, U.S.                 Jun 20, 08            confirmed.              

    Flint Hills Corpus         N     May 27, 08   300,000  FCC, sulfur recovery    
    Christi                            to                  units shut after loss of steam.
    Koch Industries Inc              Jun, 08                               
    Texas, U.S.                                                                    

    Valero Paulsboro           U     May 26, 08   195,000  FCC shuts because of a  
    Valero Energy Corp                 to                  leak. Restart confirmed.
    New Jersey, U.S.                 Jun 01, 08                                    

    Conoco Sweeny              P     May 19, 08   216,000  Hydrotreater for        
    Petroleos de                       to                  distillates shuts for   
    Venezuela SA,                    May 31, 08            catalyst change.        
    ConocoPhillips                                                                 
    Texas, U.S.                                                                    

    Chevron El Segundo         P     May 16, 08   260,000  CDU, 70,000 b/d capacity
    Chevron Corp                       to                  shuts for `several weeks’
    California, U.S.                 Jun 22, 08            of maintenance. Restart confirmed.              

    Sunoco Philadelphia        U     May 16, 08   330,000  CDU, gulfiner units shut.
    Sunoco Inc                         to                  Restarts confirmed June 4.
    Pennsylvania, U.S.               Jun 04, 08                                

    Valero Three Rivers        P     May 16, 08    95,000  FCC shuts for 10 days of
    Valero Energy Corp                 to                  maintenance.            
    Texas, U.S.                      May 26, 08                                    

    Countrymark Mount          P     May, 08       23,500  Vacuum tower starts     
    Vernon                             to                  production mid-May, raising    
    Countrymark                      May, 08        capacity by 3,000 b/d. Fuel
    Cooperative Inc                                       output to rise by 45 million gallons
    Indiana, U.S.                                          a year, mostly diesel.    

    Valero Wilmington          P     May 11, 08   135,000  Partial shutdown after  
    Valero Energy Corp                 to                  power failure.          
    California, U.S.                 May 18, 08                                    

    Delek LaGloria             U     May 11, 08    58,000  FCC rates cut by boiler 
    Delek US Holdings Inc              to                  failure. Restart        
    Texas, U.S.                      May 16, 08            confirmed.              

    Shell Martinez             U     May 09, 08   165,000  Hydrocracker shuts for a
    Royal Dutch Shell PLC              to                  week.                   
    California, U.S.                 May 16, 08                                    

    Shell Canada Sarnia        U     May 08, 08    71,820  Runs cut as unit outage 
    Royal Dutch Shell PLC              to                  curbed gasoline production       
    Ontario, Canada                  May 17, 08        More specific details not available.  

    Hovensa St. Croix          N     May 08, 08   495,000  CDU shut for unscheduled
    Petroleos de                                to                        repairs.                
    Venezuela SA, Hess               May 16, 08                                    
    Corp                                                                           
    US Virgin Islands, U.S.                                                                                                             

    Navajo Artesia             U     May 07, 08    75,000  FCC shut after          
    Holly Corp                         to                  malfunction. Restart    
    New Mexico, U.S.                 May 24, 08            confirmed.              

    Flint Hills Corpus         P     May 05, 08   300,000  Sulfur recovery unit No.
    Christi                                      to                  2 shuts for maintenance.
    Koch Industries Inc              May 15, 08                                    
    Texas, U.S.                                                                    

    Valero Corpus Christi      P     May 02, 08    38,000  CDU, Vaccum units shut  
    West                               to                  for two weeks as of May 
    Valero Energy Corp               May 16, 08            2. Restart confirmed.   
    Texas, U.S.                                                                    

    Holly Woods Cross          N     May 01, 08    26,000  Alkylation unit shut    
    Holly Corp                         to                  after fire. Restart     
    Utah, U.S.                       May 08, 08            confirmed.              

    Total Port Arthur          P     Apr 30, 08   240,000  Sulfur recovery unit and
    Total SA                           to                  units 804, 823, 824 and 
    Texas, U.S.                      May, 08               825 shut.               

    BP Carson                  U     Apr 28, 08   265,500  Hydrodesulfurization unit
    BP PLC                             to                  breakdown. Restart      
    California, U.S.                 May 01, 08            confirmed.              

    BP Texas City              P     Apr 25, 08   470,000  FCC No. 1, alkylation,  
    BP PLC                             to                  coker units shut.       
    Texas, U.S.                      May 28, 08                                    

    Imperial Oil Sarnia        U     Apr 25, 08   121,000  Runs cut by boiler      
    Exxon Mobil Corp                   to                  failure and repair.     
    Ontario, Canada                  May, 08                                       

    Murphy Superior            P     Apr 23, 08    35,000  Full shutdown to last   
    Murphy Oil Corp                    to                  about a month.          
    Wisconsin, U.S.                  May 25, 08                                    

    Total Port Arthur          U     Apr 21, 08   240,000  Hydrotreater rates cut  
    Total SA                           to                  because of malfunction
    Texas, U.S.                      Apr, 08                                       

    Alon Big Spring            N     Apr 19, 08    70,000  Sulfur recovery unit No.
    Alon Israel Oil Co                 to                  2 shut down.            
    Ltd                              Apr, 08                                       
    Texas, U.S.                                                                    

    Flint Hills Corpus         U     Apr 18, 08   300,000  Sulfur recovery unit shut
    Christi                            to                  for unplanned  maintenance.         
    Koch Industries Inc              Apr, 08                         
    Texas, U.S.                                                                    

    Valero Norco St            N     Apr, 08      190,000  FCC runs cut amid       
    Charles                            to                  slumping margins.       
    Valero Energy Corp               May, 08                                       
    Louisiana, U.S.                                                                

    BP Cherry Point            P     Apr 15, 08   232,000  Cokers, reformers shut  
    BP PLC                                   to            mid-April to mid-May in planned
    Washington, U.S.                 May 19, 08   maintenance. Two cokers and two reformers
                                                           involved. Only one unit will be down at a time. 
                                                           Reformer restart confirmed.              

    Wynnewood OK               P     Apr, 08       70,000  Shutdown to expand      
    Gary-Williams Energy               to                  capacity to 70,000      
    Co                               May 15, 08            barrels a day. Restart  
    Oklahoma, U.S.                                         confirmed May 13.       

    Shell Deer Park            U     Apr 14, 08   340,000  Coker, sulfur recovery  
    Royal Dutch Shell                  to                  unit faults reduce refinery runs.     
    PLC, Petroleos                   May 07, 08       Normal operations estimated for  
    Mexicanos                                                  May 5.
    Texas, U.S.                                                             

    Conoco Rodeo               N     Apr 14, 08    76,000  Partial shutdown after  
    ConocoPhillips                     to                  unspecified malfunction.
    California, U.S.                 Apr, 08               Conoco said production  
                                                           not affected.           

    Cenex Laurel               P     Apr 14, 08    55,000  Coker unit enters into  
    CHS Inc                                   to                  production.             
    Montana, U.S.                    Apr 15, 08                                    

    Exxon Mobil Torrance       P     Apr 12, 08   155,000  Alkylation unit shut for
    Exxon Mobil Corp                   to                  planned maintenance.    
    California, U.S.                 Apr 30, 08                                    

    Marathon Catlettsburg      N     Apr 11, 08   239,000  FCC shut after fire in  
    Marathon Oil Corp,                 to                  electrical substation.  
    Ashland Inc                      Apr 21, 08            Restart confirmed.      
    Kentucky, U.S.                                                                 

    BP Carson                  N     Apr 11, 08   265,500  Hydrocracker shut after 
    BP PLC                             to                  flash fire. Restart     
    California, U.S.                 Apr 14, 08            confirmed.              

    Total Port Arthur          P     Apr 10, 08   240,000  Catalyst change to      
    Total SA                           to                  unspecified unit. Partial
    Texas, U.S.                      Apr, 08               shutdown.               

    ConocoPhillips Los         P     Apr 09, 08   147,000  CDU, hydrocracker, coker
    Angeles                            to                  maintenance. Work to be completed
    ConocoPhillips                   May 23, 08     in May, ConocoPhillips said.       
    California, U.S.                         

    Sunoco Marcus Hook         N     Apr 08, 08   175,000  Full shutdown after power
    Sunoco Inc                         to                  failure. Resart sequence confirmed.
    Pennsylvania, U.S.               Apr 10, 08                         

    Alon Big Spring            N     Apr 07, 08    70,000  CDU shut after fire in  
    Alon Israel Oil Co                 to                  tank farm. Restart confirmed.    
    Ltd                              Apr 08, 08                          
    Texas, U.S.                                                                    

    Exxon Mobil Torrance       N     Apr 04, 08   155,000  Hydrotreater fire shuts 
    Exxon Mobil Corp                   to                  units. Unit restarted   
    California, U.S.                 Apr 06, 08            April 6.                

    Valero Benicia             U     Apr 03, 08   153,000  Hydrocracker shut because
    Valero Energy Corp                 to                  of leak. Restart        
    California, U.S.                 Apr 14, 08            confirmed.              

    Valero Houston             N     Apr 01, 08    90,000  Alkylation unit shut    
    Valero Energy Corp                 to                  after substation fire.  
    Texas, U.S.                      Apr 02, 08                                    

    Valero Delaware City       P     Mar 29, 08   190,200  Coker shut for 37 days  
    Valero Energy Corp                 to                  from late March to May  
    Delaware, U.S.                   May 27, 08            27. Restart confirmed.  

    Valero Wilmington          N     Mar 28, 08   135,000  FCC, alkylation shut    
    Valero Energy Corp                 to                  after leak. Unit restart
    California, U.S.                 Apr 06, 08            confirmed.              

    Valero Port Arthur         N     Mar 27, 08   325,000  Coker, hydrocracker shut
    Valero Energy Corp                 to                  after power failure.    
    Texas, U.S.                      Mar 31, 08            Units restarted March 31.

    Conoco Santa Maria         P     Mar 26, 08    44,000  Full shutdown because of
    ConocoPhillips                     to                  power failure. Conoco   
    California, U.S.                 Mar 28, 08            says refinery restarts  
                                                           3/28.                   

    PEMEX Cardenas             P     Mar 24, 08   190,000  HDD-NPI gasoline unit   
    Minatitlan                                      to            shut for upgrade. Restart
    Petroleos Mexicanos              Apr 07, 08    scheduled for first week
    Mexico                                                 of April.               

    Paramount                  P     Mar 24, 08    55,000  CDUs shut for 24-hours  
    Alon USA Energy Inc                to                  planned maintenance to  
    California, U.S.                 Mar 25, 08            replace an amine boiler.
                                                                   Two units idled         

    LyondellBasell             U     Mar 21, 08   287,000  FCC shut for unplanned  
    Houston                                    to                maintenance. Refinery to
    Lyondell Chemical Co             Apr 29, 08    operate at reduced rates
    Texas, U.S.                                            during repairs. Shutdown
                                                           had been planned to end in mid-April. Restart   
                                                           confirmed.              

    United Warren              N     Mar 20, 08    65,000  Vacuum distillation fire
    United Refining Co                 to                  cuts production. Normal 
    Pennsylvania, U.S.               Mar 23, 08            operations confirmed March 23.                   

    Valero Corpus Christi      N     Mar 19, 08   110,000  FCC shut week of March 17
    East                                            to                  on poor margins, Valero 
    Valero Energy Corp               May 19, 08            said. Restart process   
    Texas, U.S.                                            began mid May.          

    Valero Delaware City       U     Mar 17, 08   190,200  FCC rates reduced to    
    Valero Energy Corp                 to                  repair boiler.          
    Delaware, U.S.                   Mar 24, 08                                    

    Valero Quebec City         P     Mar, 08      215,000  CDU maintenance to cut  
    Valero Energy Corp                 to                  output by 50,000 bbl/day
    Quebec, Canada                   May, 08               for about 42 days. Unit 
                                                           restart confirmed.      

    Petro-Canada Montreal      P     Mar 15, 08   105,210  CDU shut for one week   
    Petro-Canada                       to                  starting mid-March, FCC 
    Quebec, Canada                   Apr 30, 08            closed for six weeks.   

    Motiva Convent             P     Mar, 08      235,000  Hydrocracker shutdown.  
    Motiva Enterprises                 to                  Restart confirmed.      
    LLC                              Apr 23, 08                                    
    Louisiana, U.S.                                                                

    Conoco Wood River          P     Mar, 08      306,000  FCC maintenance shutdown.
    EnCana Corp,                       to                                          
    ConocoPhillips                   Apr 09, 08                                    
    Illinois, U.S.                                                                 

    Exxon Mobil Beaumont       P     Mar 13, 08   363,100  FCCU maintenance will   
    Exxon Mobil Corp                   to                  cause flaring from March
    Texas, U.S.                      May 15, 08            13 to May 15.           

    Marathon Robinson          P     Mar 11, 08   204,000  Turnaround for planned  
    Marathon Oil Corp,                 to                  maintenance and repairs,
    Ashland Inc                      Apr 30, 08            and the refinery capacity is now
    Illinois, U.S.                                         up to 204,000 bbls a day, a company 
                                                           spokeswoman said. Restart confirmed.

    Exxon Mobil Baytown        P     Mar 09, 08   563,000  FCCU 3 C Boiler shut down
    Exxon Mobil Corp                   to                  during planned maintenance.         
    Texas, U.S.                      Apr 14, 08           

    Shell Canada Scotford      P     Mar 07, 08   100,000  Runs cut because of lack
    Royal Dutch Shell PLC              to                  of feedstock. Normal    
    Alberta, Canada                  Mar 17, 08            operations confirmed March 17.             

    Marathon Detroit           P     Mar 05, 08   100,000  Full shutdown for planned
    Marathon Oil Corp,                 to                  maintenance. Completion 
    Ashland Inc                      May, 08               of restart confirmed.   
    Michigan, U.S.                                                                 

    Valero Delaware City       P     Mar, 08      190,200  Coker 50,000 bbl/day shut
    Valero Energy Corp                 to                  for 37-days planned maintenance    
    Delaware, U.S.                   Apr, 08              during March/April 2008.       

    Valero Memphis             P     Mar, 08      190,000  FCCU 69,000 bbl/day shut
    Valero Energy Corp                 to                  down for 15-days planned
    Tennessee, U.S.                  Mar 20, 08            maintenance. Unit restart
                                                           confirmed March 26.     

    Big West Oil               N     Mar 04, 08    68,000  Coker shut after a power
    Bakersfield                        to                  outage affected “Area  
    Flying J Oil & Gas               Mar, 08               3” About 500 pounds of 
    Inc                                                    sulfur dioxide was released. An unspecified     
    California, U.S.                                   unit was partially shut down. 

    Valero Corpus Christi      P     Mar 04, 08   110,000  Fire shut a diesel      
    East                                           to             hydrogen desulfurization
    Valero Energy Corp               Mar 10, 08       unit in Complex 1 of the
    Texas, U.S.                                            refinery’s west plant.  

    Suncor Commerce City       P     Mar 03, 08    31,000  Planned maintenance cut 
    (VLO)                              to                  total capacity 40       
    Suncor Energy Inc                Mar 21, 08            percent, a Suncor       
    Colorado, U.S.                                         spokesman said.         

    Suncor Commerce City       P     Mar 03, 08    62,000  Planned maintenance cut 
    Suncor Energy Inc                  to                  total output 40 percent,
    Colorado, U.S.                   Mar 21, 08            a Suncor spokesman said.

    Frontier El Dorado         P     Mar 01, 08   112,000  CDU shut for 38 days of 
    Frontier Oil Corp                  to                  maintenance and installation of new        
    Kansas, U.S.                     Apr 08, 08       vacuum tower. Unit restart confirmed.           

    Imperial Oil               U     Mar, 08      184,000  Runs cut after fault in 
    Strathcona                         to                  gasoline unit led to fuel
    Exxon Mobil Corp                 Apr 06, 08            shortates in Western    
    Alberta, Canada                                        Canada. Restart of unit 
                                                           confirmed.              

    Citgo Corpus Christi       P     Mar 01, 08   156,000  Sulfur recovery unit,   
    Petroleos de                             to               mixed distillate hydrotreater       
    Venezuela SA                         Apr, 08        and coker effectiver March 1, 2008 
    Texas, U.S.                                           at West Plant. East plant CDU shutdown
                                                           and vacuum maintenance. SRU started
                                                           as of April 1. Coker as of April 8. CDU and VDU 
                                                           restarted as of April 10

    BP Texas City              P     Mar, 08      470,000  Alkylation unit (45,000 
    BP PLC                             to                  b/d) restarts April 14 after 
    Texas, U.S.                      Mar 14, 08       maintenance. Second alkylation
                                                           unit of 22,000 then to be taken out of 
                                                           service for repairs.    

    Conoco Ponca City          P     Feb, 08      187,000  FCCU restarted March 15 
    ConocoPhillips                     to                  after weeks of planned  
    Oklahoma, U.S.                   Mar 15, 08            maintenance.            

    Valero Benicia             U     Feb, 08      153,000  FCC of 72,000 bbl/day   
    Valero Energy Corp                 to                  shut for unplanned      
    California, U.S.                 Mar, 08               repairs on Feb. 28, 2008.                    

    Valero Benicia             U     Feb 28, 08   153,000  FCCU leak forced Valero 
    Valero Energy Corp                 to                  to shut the unit for    
    California, U.S.                 Mar 01, 08            unplanned repairs.      

    Pasadena                   N     Feb 27, 08   106,500  Full shutdown Feb. 27   
    Nationale A                        to                  after a “complete power”
    Portefeuille                     Mar 05, 08            failure. FCCU shut down 
    Texas, U.S.                                            following a power outage.

    Valero Norco St            P     Feb 21, 08   190,000  FCCU unit shut down about
    Charles                                    to              2/21/08, reducing production by       
    Valero Energy Corp               Mar 12, 08     100,000  bbl/day for 20 days. 
    Louisiana, U.S.                                           

    Pasadena                   U     Feb 21, 08   106,500  FCCU shut down for      
    Nationale A                        to                  specific repairs.       
    Portefeuille                     Feb 22, 08                                    
    Texas, U.S.                                                                    

    Exxon Mobil Beaumont       N     Feb 20, 08   363,100  No. 5 Coke drum shut to 
    Exxon Mobil Corp                   to                  repair a leak on Feb. 20,
    Texas, U.S.                      Feb 28, 08            2008, and resumed       
                                                           operation on Feb. 28.   

    Conoco Sweeny              P     Feb 19, 08   216,000  Regenerative thermal    
    Petroleos de                       to                  oxidizer (RTO) which controls    
    Venezuela SA,                    Feb 20, 08     vapors from the Wastewater
    ConocoPhillips                                        Treater unit shut for maintenance.
    Texas, U.S.                                              

    Citgo Corpus Christi       P     Feb 18, 08   156,000  Unibon unit shut for    
    Petroleos de                           to                  planned maintenance. It’s
    Venezuela SA                     Feb 24, 08     also known as a gasoil hydortreater. 
    Texas, U.S.                                           

    Tesoro Kapolei             N     Feb 16, 08    95,000  Full shutdown after fire.
    Tesoro Corp                        to                  Units restarted Feb. 18 
    Hawaii, U.S.                     Feb 18, 08                                    

    Hovensa St. Croix          P     Feb 14, 08   495,000  Planned maintenance. The
    Petroleos de                       to                  two largest crude units 
    Venezuela SA, Hess               Mar, 08               were not shut.          
    Corp                                                                           
    US Virgin Islands, U.S.                                                                                                           

    Total Port Arthur          P     Feb 13, 08   240,000  Reformer shut for planned
    Total SA                           to                  maintenance; and work should  
    Texas, U.S.                      Feb 29, 08      be finished in a couple weeks.       

    Sunoco Philadelphia        N     Feb 13, 08   330,000  Power cut shut          
    Sunoco Inc                         to                  unspecified units.      
    Pennsylvania, U.S.               Feb 13, 08                                    

    Delek LaGloria             N     Feb 12, 08    58,000  Sulfur recovery unit shut
    Delek US Holdings Inc              to                  down after a mechanical 
    Texas, U.S.                      Feb, 08               upset.                  

    Shell Canada Scotford      N     Feb 12, 08   100,000  Runs cut because of     
    Royal Dutch Shell PLC              to                  reduced supplies from oil
    Alberta, Canada                  Feb 20, 08            sand plant.             

    PEMEX Jaime Salina         N     Feb 12, 08   290,000  Earthquake shuts 26     
    Cruz                                             to            processing plants at its
    Petroleos Mexicanos                Feb 14, 08      Salina Cruz refinery.   
    Mexico                                                 Pemex restarted operations after finding
                                                           minimal damage.         

    Conoco Borger              P     Feb 11, 08   146,000  FCC repair to           
    ConocoPhillips,                    to                  electrostatic           
    EnCana Corp                      Mar 03, 08       precipitators on the Unit 29.
    Texas, U.S.                                                           

    Flint Hills Corpus         P     Feb 11, 08   300,000  Planned maintenance     
    Christi                                      to                  caused flaring.         
    Koch Industries Inc              Feb 21, 08                                    
    Texas, U.S.                                                                    

    Valero Delaware City       N     Feb 10, 08   190,200  Full shutdown after power
    Valero Energy Corp                 to                  cut. Power was restored 
    Delaware, U.S.                   Feb 11, 08            to the crude unit, coker,
                                                           and catalytic cracker, and these units restarted
                                                           on 2/11/08. On 2/25/08, the hydrocracker was the
                                                           last main unit to resume operation, Valero said. 

    Lake Charles               N     Feb 10, 08   320,000  Power outage disrupted  
    Petroleos de                       to                  operations.             
    Venezuela SA                     Feb 11, 08                                    
    Louisiana, U.S.                                                                

    Chevron Richmond           P     Feb 07, 08   257,200  Reformers. Major planned
    Chevron Corp                       to                  maintenance scheduled for
    California, U.S.                 Mar, 08               1st Qtr 2008. Two       
                                                           reformer units replaced 
                                                           during this period.     

    Paramount                  P     Feb 07, 08    55,000  CDUs (two of four) shut;
    Alon USA Energy Inc                to          refinery is undergoing planned  
    California, U.S.                 Feb, 08        maintenance to improve gasoline yields,  
                                                           an Alon spokesman said. 

    ConocoPhillips Los         P     Feb 07, 08   147,000  Sulfur recovery units   
    Angeles                            to                  shut down caused flaring.
    ConocoPhillips                   Feb, 08                                       
    California, U.S.                                                               

    Delek LaGloria             N     Feb 07, 08    58,000  Mechanical failure shut a
    Delek US Holdings Inc              to                  boiler and reduced rates
    Texas, U.S.                      Feb 08, 08            into a fluid catalytic  
                                                           cracking unit           

    Shell Deer Park            N     Feb 05, 08   340,000  Coker (85,000 bbl/day)  
    Royal Dutch Shell                  to                  unit shut down after the
    PLC, Petroleos                   Mar 05, 08         anti-surge valve opened,
    Mexicanos                                              Shell said.             
    Texas, U.S.                                                                    

    Valero Wilmington          P     Feb 05, 08   135,000  FCCU and alkylation unit
    Valero Energy Corp                 to                  shut down for about 10  
    California, U.S.                 Feb 14, 08            days planned maintenance,
                                                           a Valero spokesman said.

    Valero Port Arthur         P     Feb 04, 08   325,000  Coker(105,000 bbl/day)  
    Valero Energy Corp                 to                  maintenance.            
    Texas, U.S.                      Feb 29, 08                                    

    Valero Norco St            P     Feb, 08      190,000  CDU maintenance to cut  
    Charles                            to                  about 100k bbl/day for 20 days.
    Valero Energy Corp               Feb, 08                                 
    Louisiana, U.S.                                                                

    Wynnewood OK               N     Feb 01, 08    70,000  Fire caused by a leak in
    Gary-Williams Energy               to                  a depropanizer unit. The
    Co                               Feb 01, 08            fire was extinguished and
    Oklahoma, U.S.                                         refinery rates weren’t  
                                                           reduced, a company      
                                                           spokesman said.         

    Tesoro Anacortes           P     Jan 31, 08   108,000  Planned maintenance     
    Tesoro Corp                        to                                          
    Washington, U.S.                 Feb, 08                                       

    Conoco Wood River          P     Jan 31, 08   306,000  Flare gas recovery      
    EnCana Corp,                       to                  compressor shut for     
    ConocoPhillips                   Jan 31, 08            repairs.This will not   
    Illinois, U.S.                                         affect production.      

    BP Texas City              N     Jan 30, 08   470,000  FCC (120,000 bbl/day)   
    BP PLC                             to                  restarted after a Jan. 30
    Texas, U.S.                      Mar 07, 08            electrical fault. Crude 
                                                           unit (250,000 bbl/day pipestill 3B) restarted 
                                                           March 7 after shutting down following Hurricane
                                                           Katrina in 2005.        

    Valero Aruba               N     Jan 25, 08   275,000  Full shutdown after     
    Valero Energy Corp                 to                  vacuum tower fire.      
    Aruba                            May 28, 08            Partial operations      
                                                           resumed by Feb. 5. Vacuum
                                                           crude distillation unit restarted May 28.       

    Big West Oil               P     Jan, 08       68,000  Planned maintenance on an
    Bakersfield                        to                  unknown unit is scheduled
    Flying J Oil & Gas               Feb, 08               to last from 7 to 10 days
    Inc                                                    during late Jan. 2008, a
    California, U.S.                                       Flying J manager said.  

    Total Port Arthur          N     Jan 24, 08   240,000  Sulfur recovery unit went
    Total SA                           to                  down causing an emission
    Texas, U.S.                      Jan 24, 08            release. The shell claus
                                                           off-gas treating unit was
                                                           restarted as soon as    
                                                           possible, Total said.   

    LyondellBasell             P     Jan 23, 08   287,000  Aromatics unit shut by  
    Houston                                    to              fire ahead of planned   
    Lyondell Chemical Co             Mar 20, 08      maintenance scheduled to
    Texas, U.S.                                            begin the week of Jan.28, a LyondellBasell    
                                                           Industries spokeswoman said.                   

    Suncor Sarnia              P     Jan 23, 08    80,000  Runs cut 30% because of 
    Suncor Energy Inc                  to              fault in new diesel hydrotreater,   
    Ontario, Canada                  Jan, 08         lack of hydrogen supply.        

    Valero Corpus Christi      N     Jan 23, 08   110,000  Vapor recovery compressor
    East                                           to               located on the No. 4 crude unit  
    Valero Energy Corp               Jan 29, 08         shut at Complex 7 on Jan. 23     
    Texas, U.S.                                               after an electrical short circuit.              

    Total Port Arthur          P     Jan 21, 08   240,000  Refinery planned        
    Total SA                                to                  maintenance             
    Texas, U.S.                          Mar 08, 08                                    

    Conoco Borger              P     Jan 21, 08   146,000  Hydrogen desulfurization
    ConocoPhillips,                         to                  unit shut down Jan. 21 to
    EnCana Corp                      Jan 26, 08            repair a leak is expected
    Texas, U.S.                                            to return to normal with a week.
                                                          It will have minimal effect on production.                 

    Exxon Mobil Baytown        P     Jan 18, 08   563,000  Delayed Coking unit shut
    Exxon Mobil Corp                   to                  for planned maintenance.
    Texas, U.S.                      Mar 14, 08                                    

    Shell Deer Park            P     Jan 17, 08   340,000  FCC, gasoline           
    Royal Dutch Shell                  to                  hydrotreater, alkylation
    PLC, Petroleos                   Mar 05, 08     facility and three sulfur
    Mexicanos                                              recovery plants shut    
    Texas, U.S.                                            during maintenance.     

    Motiva Port Arthur         U     Jan 14, 08   285,000  Waste-heat boiler       
    Motiva Enterprises                     to              shutdown for about 20 days  
    LLC                                     Feb 03, 08      to repair a leak. A scrubber
    Texas, U.S.                                           will be bypassed, causing flaring
                                                           through Feb. 3.         

    BP Texas City              N     Jan 14, 08   470,000  Hydrocracker            
    BP PLC                             to                  (ultracracker) explosion
    Texas, U.S.                      Jan, 08               kills one worker.       

    Exxon Mobil Baytown        P     Jan 12, 08   563,000  CDU maintenance Jan. 12 
    Exxon Mobil Corp                   to                  to March 31. Coker      
    Texas, U.S.                      Mar 31, 08            restarted March 14. An  
                                                           FCCU also repaired while
                                                           maintenance performed on the coker.              

    BP Carson                  P     Qtr 1, 08    265,500  FCC Upgrade to          
    BP PLC                                 to           electrostatic precipitator.          
    California, U.S.                   Mar 28, 08  Several units to be upgraded in  
                                                          2008 to cut sulfur in gasoline, diesel.
                                                           Sulfur Plant, alkylation repairs also planned.           

    Valero Aruba               N     Jan 08, 08   275,000  Full refinery shutdown  
    Valero Energy Corp                 to                  after a power disruption
    Aruba                            Jan 15, 08            on Jan. 8.              

    Marathon Garyville         P     Jan, 08      275,000  FCC shut down for planned
    Marathon Oil Corp,                 to                  maintenance sometime    
    Ashland Inc                      Feb, 08               during the week of Jan. 
    Louisiana, U.S.                                        7. Timeline for restart 
                                                           not detailed.           

    Alon Big Spring            P     Jan 07, 08    70,000  Hydrotreater 22,000     
    Alon Israel Oil Co                 to                  bbl/day, Reformer 21,000
    Ltd                              Jan 14, 08            bbl/day, Gasoil         
    Texas, U.S.                                            hydrotreater 6,500      
                                                           bbl/day, jet fuel unit  
                                                           4,500 bbl/day shut for  
                                                           maintenance Jan. 7.     

    Valero Corpus Christi      P     Jan, 08      110,000  CDU maintenance to cut  
    East                               to                  40,000 bbl/day for 14 days during  
    Valero Energy Corp               Jan, 08      January at its west plant. 
    Texas, U.S.                                                   

    Exxon Mobil Baton          P     Jan 04, 08   488,600  FCC, alkylation units   
    Rouge                                        to              turnaround planned to   
    Exxon Mobil Corp                      Feb, 08        last several weeks and  
    Louisiana, U.S.                                        end around the end of   
                                                           February, ExxonMobil    
                                                           said.                   

    Chalmette LA               P     Jan 04, 08   184,000  FCCU, alkylation unit and
    Petroleos de                       to                  other units will be     
    Venezuela SA, Exxon              Feb 27, 08            undergoing planned      
    Mobil Corp                                             maintenance until the end
    Louisiana, U.S.                                        of February.            

    Sunoco Inc Eagle           P     Qtr 1, 08    150,000  CDU turnaround, brought 
    Point Refinery                     to                  forward from second half
    Sunoco Inc                       Qtr 1, 08             of year.                
    New Jersey, U.S.                                                               

    Sunoco Toledo              P     Qtr 1, 08    150,000  Planned maintenance will
    Sunoco Inc                         to                  reduce production 2.5   
    Ohio, U.S.                       Qtr 1, 08             million barrels during Qtr 1, 08.              

    Sunoco Philadelphia        P     Qtr 1, 08    330,000  CDU, FCC unit maintenance
    Sunoco Inc                         to                  completed.              
    Pennsylvania, U.S.               Qtr 1, 08                                     

    –Editor: Dan Stets.
    To contact the reporter on this story:
    Robert Tuttle in New York at +1-212-617-3465 or
    rtuttle@bloomberg.net

  • #6716

    Charles Randall
    Participant

    Here is July update on North America Refinery T/A Schedules – just a few changes from June 2008 tables. But it is Still a Tough list when some new reasons downtime includes Earthquakes and Economics!
     
    And it seems that lot unplanned S/D (not connected with fires, explosions or leaks) continue revolve around power failures, FCC units & Sulfur Units. Almost a shame for the Coking refineries to have lot power issues with today’s options for Petcoke CFB or Polygen Gasifier and today’s power & byproduct prices – also lot failures are around same group plants (Delaware, Aruba, La Gloria, Corpus, Deer Park & Houston).
     
    But the all time poster Refinery for power failure is still Valero Delaware’s with it’s Power problems from GE (old Texaco) Gasification unit – a lot lost refinery downtime.
    Regards

  • #6712

    Charles Randall
    Participant

    <Valero News Release on Shutdown Pt Arthur  & these agree with the Bloomberg NA tables – CER>
    Business briefs Web Posted: 07/10/2008 07:56 PM CDT

    Total shuts 9 units at Port Arthur refinery
    Total SA, Europe’s largest oil refiner, said it shut nine units, including a distillate hydrotreater, at its Port Arthur refinery in Texas and will restart them after 72 hours.
    The shutdowns began Wednesday at 6 p.m. local time and are scheduled to end at 6 p.m. Saturday, according to a filing with state regulators. The affected units were 804, 805, 810, 819, 822, 823, 824, 825 and 836.
    The reasons for the shutdowns and names of the units weren’t stated in the filing. The closure resulted in the release of pollutants including carbon monoxide and sulfur dioxide.
    The plant can process about 240,000 barrels of crude oil a day, according to U.S. Energy Department data.
    Valero plans repairs at Delaware refinery
    San Antonio-based Valero Energy Corp., said it plans a maintenance period, or turnaround, at its Delaware City, Del., refinery in the fourth quarter that will include the 180,000-barrel-a-day crude unit.
    Whether other units are included is to be determined, Valero spokesman Bill Day said Thursday.
    The company plans to release a maintenance schedule for its North American refineries during the next two quarters on July 29, when it issues its quarterly earnings statement, Day said.
    The Delaware plant can process 190,200 barrels of oil a day, according to government and company data.
     
     

  • #6703

    Charles Randall
    Participant

    < 3 UPdates for NA Shutdowns Table>
     
    North American Planned, Unplanned Refinery Shutdowns (Table)
     (New York)
    By Robert Tuttle
         July 22, 2008 (Bloomberg) —  a table of scheduled and unplanned 
         Shutdown Type: P: Planned, U: Unplanned, N: Non-maintenance

    Refinery                                     Refinery                          
    Owner                  Shutdown              Capacity                          
    Location                 Type    Period        b/d     Notes                   
    ——————————————————————————–
    New Information:

    Exxon Mobil Joliet         P     Aug, 08      240,000  SRU shuts for           
    Exxon Mobil Corp                   to                  maintenance.            
    Illinois, U.S.                   Oct, 08                                       

    Shell Deer Park            N     Jul 17, 08   340,000  FCC rates reduced after 
    Royal Dutch Shell                  to                  power disruption. Restart
    PLC, Petroleos                   Jul 19, 08            confirmed.              
    Mexicanos                                                                      
    Texas, U.S.                                                                    

    BP Toledo                  P     Jul 15, 08   155,000  Hydrocracker, reformer  
    BP PLC                             to                  shut for maintenance.   
    Ohio, U.S.                       Sep 04, 08                   