Coke Handling Bridge Crane

Home Forums Coking Maintenance Pumps, Valves, Rotary Joints, Cranes Cranes Coke Handling Bridge Crane

This topic contains 3 replies, has 3 voices, and was last updated by  ted pivo 11 years, 7 months ago.

  • Author
    Posts
  • #4055

    Lucibar Davalillo
    Participant

    Are new cokers best practice to install 2 bridge cranes instead one? Does anybody has an estimated price break-down can be shared? Is it any worth from reliability and mainteinability point of view? 
     
    Thanks,
    Lucky

  • #7201

    ted pivo
    Member

    we are presently building a new coker, I have talked with 2 crane vendors and both recommend 2 cranes for reliability . Make sure you have a maintenance area for working on this  equipment. In the electrical room for the resistors banks make sure you install an overhead trolley beam for lifting as they are quite heavy. always keep a spare crane bucket as these are long items for repair. make sure your lifting cables have the plastic coating increases relability
     
    have you considered  automating the crane operation?

  • #7200

    Claus Graf
    Participant

    We had two overhead cranes in a 4 drum coker. Our coke pit had walls around, and the coke crusher was high, making the use of a front end loader (in case of emergency) not an option.
     
    1. I agree with woodshop on the plastic coating. The cables that will wear out faster are the ones that open and close the bucket. Have spare cables ready.
     
    2. Guide rail alignment is critical for reliable operation. Also, closely review the beam support for the rails.
     
    3. Plan on getting a control system that will minimize stress on the crane structure by means of controlling each motor operation independently. This will prevent one side of the crane trying to move ahead of the other side.
     
    4. Spare bucket is required. Once you have to replace your first bucket, you can repair the old one.
     
    5. Make sure there is enough clearance between the maintenance area roof and the crane for easier access and safety.
     
    6. Operator control cabin location should be decided based on safety and operator preference. Our cabin and bucket moved together and the steam from the coke hindered vision.
     
    7. You want large diameter roller on the bucket to prevent/minimize damage to the opening/closing cables.
     
    8. With two cranes you need an anti-collision device that will disable the cranes if the get too near.
     
    9. Get the best seat you can  for the safety and comfort of the crane operator.
     
    Regards,
     
    CG
     
     

  • #6706

    Claus Graf
    Participant

    Review different bucket manufacturers experience with materials for the service. Compare different designs, capacities and bucket weight. Make sure you have spare capacity available in case you need to move more coke in the future or you replacement bucket is heavier.
     
    Regards, CG