This topic contains 1 reply, has 1 voice, and was last updated by  Charles Randall 12 years, 5 months ago.

  • Author
    Posts
  • #3562

    Charles Randall
    Participant

    Table Of Asia Refinery Maintenance Schedule

    Update June 22, 2008 TOKYO -(Dow Jones)- The following table lists maintenance schedules and outages for oil refineries in Asia.  Additional information will be added as it becomes available. Asia Refinery Maintenance Schedule For 2008
    Country Company Location Unit(B/D) Period/Duration
    China Sinopec Jiujiang CDU Nov 11-early Feb 2008
    (50,000)
    China Sinopec Yangzi CDU Mar, 40 days
    (70,000)
    China Sinopec Jingmen CDU End-Feb, 30 days
    (70,000)
    China Sinopec Wuhan CDU Mar 15, 20 days
    (70,000)
    China Sinopec Maoming Hydrocracker Apr 16-mid-May

    China PetroChina Lanzhou CDU Jul, one month
    (60,000)
    China PetroChina Lanzhou Delay Coker Jul, one month
    (28,000)
    China PetroChina Dalian CDU 3Q, one month
    (200,000)
    India HPCL Mumbai whole refinery Apr 21, 35 days
    (110,000)
    Indonesia Pertamina Dumai CDU at 60% capacity Jan 17-21
    (120,000)
    Indonesia Pertamina Balongan whole refinery Oct, 45 days
    (125,000)
    Japan Cosmo Oil Chiba No.2 CDU Apr 25-Jun 30
    (130,000)
    Japan Nippon Oil Negishi CDU May 24, one month
    (Part of 340,000)
    Japan Nippon Oil Sendai CDU Jun 8, one month
    (145,000)
    Japan Nihonkai Oil Toyama CDU May 19-Jun 21
    (60,000)
    Japan Kyushu Oita No.3 CDU May 20-Jun 21
    (136,000)
    Japan Idemitsu Hokkaido CDU Jun 16-26
    (140,000)
    Japan Nansei Nishihara CDU Jun 18-Jul 11
    (100,000)
    Japan Taiyo Oil Shikoku No.1 CDU Jun 25-Jul 15
    (88,000)
    Japan Taiyo Oil Shikoku No.2 CDU Jun 24-Jul 13
    (32,000)
    Japan Cosmo Oil Sakai CDU Aug 22-Sep 30
    (80,000)
    Japan Cosmo Oil Chiba No.1 CDU Sep 13-Nov 9
    (110,000)
    Japan Cosmo Oil Yokkaichi No.5 CDU Sep 28-Nov 14
    (90,000)
    Japan Nippon Oil Mizushima CDU Sep, 27 days
    (Part of 250,000)
    Japan Nippon Oil Negishi CDU Sep, 39 days
    (Part of 340,000)
    Japan Seibu Yamaguchi CDU Early Sep, 37 days
    (120,000)
    Japan Idemitsu Tokuyama CDU Around Oct-Nov
    (120,000)
    S Korea GS Caltex Yeosu No. 4 CDU Apr, 10 days
    (300,000)
    S Korea GS Caltex Yeosu No. 2 CDU Early Aug, one month
    (130,000)
    S Korea Hyundai Daesan No.1 CDU May 17-Jun 12
    (110,000)
    S Korea SK Energy Ulsan No.5 CDU May 19, 40 days
    (260,000)
    S Korea SK Energy Ulsan No.1 CDU Jun 10, 10 days
    (60,000)
    S Korea SK Energy Ulsan No.4 CDU Jun 10, a few days
    (240,000)
    S Korea SK Energy Ulsan No. 1 RFCC Jun (30 days)
    (56,000)
    S Korea SK Energy Incheon No.2 CDU Jun 25-early Aug
    (200,000)
    S Korea SK Energy Incheon No.1 CDU June 26, 1 month
    (75,000)
    S Korea S-Oil Onsan whole refinery Mar 24-25
    (575,000)
    Sri Lanka Ceypetco Sapugaskanda whole refinery Jan 22-Feb 29
    (50,000)
    Taiwan CPC Kaohsiung No.6 CDU Oct 26, 2007-late Apr
    (100,000)
    Taiwan CPC Kaohsiung No.8 CDU Sep 12-Nov 5
    (100,000)
    Taiwan CPC Kaohsiung VGO Hydrotreater Jan 5, TBA
    (25,000)
    Taiwan CPC Kaohsiung RFCC Jan 5-end-Apr
    (25,000)
    Taiwan CPC Kaohsiung No.2 RDS Sep 30-Nov 6
    (30,000)
    Taiwan CPC Dalin RFCC Mar 27-Apr 4
    (25,000)
    Taiwan CPC Dalin No. 3 RDS Aug 14-Sep 19
    (30,000)
    Taiwan CPC Taoyuan RFCC Early Mar, 5 days
    (50,000)
    Taiwan CPC Taoyuan No.2 RDS Sep 15-Oct 23
    (15,000)
    Taiwan Formosa Mailiao delay coker 2H Feb, 8-9 days
    (36,000)
    Taiwan Formosa Mailiao No.1 CDU Mar 10-Apr 21
    (180,000)
    Taiwan Formosa Mailiao No.1 RFCC Mar 10-Apr 27
    (84,000)
    Taiwan Formosa Mailiao No.1 RDS Mar 10-Apr 25
    (80,000)
    Taiwan Formosa Mailiao Hydrotreater Mar 10-Apr 21
    (63,000)
    Taiwan Formosa Mailiao Hydrotreater Mar 14-15
    (24,000)
    Taiwan Formosa Mailiao No.2 RDS Sep 1, 38 days
    (80,000)
    Taiwan Formosa Mailiao Hydrotreater 2H June, one week
    (42,000)
    Taiwan Formosa Mailiao No.2 RFCC Early July, 7-10 days
    (84,000)
    Taiwan Formosa Mailiao No. 2 CDU Nov, 36 days
    (180,000)
    Thailand Star Petroleum Whole refinery Nov, 40 days
    (150,000)

    Note:
    TBA – To be announced
    CDU – Crude distillation unit
    FCC – Fluid catalytic cracker
    HDS – Hydrodesulfurizer
    RFCC – Residual fluid catalytic cracker
    RDS – Residual desulfurizer

    (END) Dow Jones Newswires
    06-22-082352ET

  • #6759

    Charles Randall
    Participant

    Here is June update of Asia Refinery Maintenance schedules (Blue highlight are coking refineries).
    See coker news posting on coking.com for several new Refinery coking additions in China coming online or starting construction (ie Sinopec Quingdao, Sinopec Qilu, CNOOC Huizhou, Sinopec Wuhan, Sinopec Nanjing; some are just additional units to existing coking sites & others are inital coking units for heavy oil upgrading)
     
    Regards
    Charlie Randall