    Table Of Asia Refinery Maintenance Schedule
    SINGAPORE -(Dow Jones) April 1, 2008 –
    The following table lists maintenance schedules and outages for oil refineries in Asia.
    Additional information will be added as it becomes available. Asia Refinery Maintenance Schedule For 2008
    Country Company Location Unit(B/D) Period/Duration
    China Sinopec Jiujiang CDU Nov 11,2007-early Feb 2008
    (50,000)
    China Sinopec Yangzi CDU Mar, 40 days
    (70,000)
    China Sinopec Jingmen CDU End-Feb, 30 days
    (70,000)
    China Sinopec Wuhan CDU Mar 15, 20 days
    (70,000)
    China PetroChina Dalian CDU 3Q, one month
    (200,000)
    Indonesia Pertamina Dumai CDU,at 60% capacity Jan 17-21
    (120,000)
    S Korea GS Caltex Yeosu No. 4 CDU April, 10 days
    (270,000)
    S Korea GS Caltex Yeosu No. 2 CDU Early Aug, one month
    (130,000)
    S Korea Hyundai Daesan No.1 CDU May 17 – Jun 12
    (110,000)
    S Korea SK Energy Ulsan No.5 CDU May 19, 40 day
    (260,000)
    S Korea SK Energy Ulsan No.1 CDU June 10, 10 days
    (60,000)
    S Korea SK Energy Ulsan No.4 CDU June 10, a few days
    (240,000)
    S Korea SK Energy Incheon No.2 CDU Jun 25 – Aug 1
    (200,000)
    S Korea S-Oil Onsan whole refinery Mar 24-25
    (575,000)
    Sri Lanka Ceypetco Sapugaskanda whole refinery Jan 22-Feb 29
    (50,000)
    Taiwan CPC Kaohsiung No.6 CDU Oct 26, 2007, TBA
    (100,000)
    Taiwan CPC Kaohsiung VGO Hydrotreater Jan 5, TBA
    (25,000)
    Taiwan CPC Kaohsiung RFCC Jan 5 – end-April
    (25,000)
    Taiwan CPC Dalin RFCC Mar 27, 2 weeks
    (25,000)
    Taiwan CPC Dalin Reformer June or August
    (30,000)
    Taiwan CPC Taoyuan RFCC Early March, 5 days
    (50,000)
    Taiwan Formosa Mailiao delay coker 2H Feb, 8-9 days
    (36,000)
    Taiwan Formosa Mailiao No.1 CDU Mar 10, 40 days
    (180,000)
    Taiwan Formosa Mailiao No.1 RFCC Mar 10 – end-Apr
    (80,000)
    Taiwan Formosa Mailiao No.1 RDS Mar 10 – end-Apr
    (80,000)
    Taiwan Formosa Mailiao Hydrotreater Mar 10-end Apr
    (63,000)
    Taiwan Formosa Mailiao Hydrotreater Mar 14-15
    (24,000)
    Taiwan Formosa Mailiao No. 2 CDU Nov, 40 days
    (180,000)
    Japan Nippon Oil Marifu CDU Mar 15 – Apr 24
    (127,000)
    Japan Nippon Oil Negishi CDU Early May, 34 days
    (Part of 340,000)
    Japan Nippon Oil Sendai CDU Late May, 38 days
    (145,000)
    Japan Kyushu Oita CDU A Month From Late May
    (136,000)
    Japan Nansei Nishihara CDU Late May to early June
    (100,000)
    Japan Taiyo Oil Shikoku No.1 CDU June 25-July 15
    (88,000)
    Japan Taiyo Oil Shikoku No.2 CDU June 24-July 13
    (32,000)
    Japan Nippon Oil Mizushima CDU Sep, 27 days
    (Part of 250,000)
    Japan Nippon Oil Negishi CDU Sep, 39 days
    (Part of 340,000)
    Japan Seibu Yamaguchi CDU Early Sep, 37 days
    (120,000)
    Japan Idemitsu Tokuyama CDU Around Oct-Nov
    (120,000)

    Note:
    TBA – To be announced
    CDU – Crude distillation unit
    FCC – Fluid catalytic cracker
    HDS – Hydrodesulfurizer
    RFCC – Residual fluid catalytic cracker
    RDS – Residual desulfurizer

    (END) Dow Jones Newswires
    04-01-080743ET
    Copyright (c) 2008 Dow Jones & Company, Inc