Update news item on IOC Panipat coking refinery that will complete another expansion by December 2009. IOC had recently doubled capacity Panipat coking refinery to 12 MT (120MBD) in 2006 which also included New Crude, Vacuum Tower & Coking Unit ( capacity of 2.4MT or ~25 MBD) and ABB Lumus did the Coking unit EPC/Technology.
It is not mentioned here but is to be expected that the Panipat fuel coker would need to be expanded as well.