Re: RE: Update Russia Bashneft Refinery Cokers

Home Forums Coking News: DCU, Upgrader 1.Coker (registered users only) Update Russia Bashneft Refinery Cokers Re: RE: Update Russia Bashneft Refinery Cokers

#4440

Anonymous

Yes, You are right. Our coke uses in steel industry as addition. The fuel gas that uses has not very well combustion heat and after increasing of capacity it a reason to add new preheater. After preheater temperature of feed is 350C. Then feed mixes with recycle (HGO) and goes to the furnace. inlet drum temperature is 467-468C (usually. it corrects by results of analysis of coke)