Our DCU is located in Eastern Asia with capacity of 36,000 bpsd(4-drums).
We operate this plant for 9 years.
We mainly process Mid-East Crude.
As feed crude change very often,it is not easy to operate this plant.
Also the coke handling system in this plant is slurry , not pit type.
Anyway thanks for your helpful information.