Refining Community Logo

RE: Drum ovh lines cleanout facilities

Home Forums Coking Design and Reliability Cokedrums, Structure, Inspection Drums Drum ovh lines cleanout facilities RE: Drum ovh lines cleanout facilities

#6244

Lucy are you talking about the drain between sp1&sp2 and sp6 & switch valve?,
These connections are typically 2 inches, in our designs We change the connection between  valve switch  & sp6 to  3 “, with connections for cleaning or removable spool
 
Best Regards
 