Seems odd that COP would have back to back Turnarounds on its two Needle coke producing refineries (~estimated combined 60-70% WW production) – but they could always have built enough green needle coke to calcine thru the T/A period and those cokers, except for feedstock HDS units, are seldom tied to crude processing units.